Through March 2024
Auth Code | Fund | Reapprop | Provisos | Current Biennium Appropriation | Budgeted Cost of Work (Allotted) | Actual Cost of Work | Outstanding Contracting Balance (Encumbered) | Total Dollars Obligated | Percent Obligated | Percent Expended | Biennium to Date Variance (Allotted - Actuals) | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
This Month | Biennium to Date | This Month | Biennium to Date | ||||||||||
20082856 - Cowlitz River Dredging | |||||||||||||
C00 | 057 | Y | N | 2,000,000 | |||||||||
40000002 - Construction Cost Assessment | |||||||||||||
C03 | 289 | Y | N | 54,000 | 27,000 | 27,000 | |||||||
40000005 - Emergency Repairs | |||||||||||||
I99 | 057 | Y | N | 2,476,000 | |||||||||
92000035 - Fircrest School Land Use Assessment | |||||||||||||
A03 | 057 | Y | N | 165,000 | 82,500 | 310 | 310 | 0.18% | 0.18% | 82,190 | |||
105 - Office of Financial Management Totals | 4,695,000 | 109,500 | 310 | 0.18% | 0.18% | 109,190% |