Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30002736 - Echo Glen-Housing Unit: Acute Mental Hea
A00 057 Y N 3,897,860 3,897,860 2,617,061 2,617,061 67% 67% 1,280,799
30003237 - Green Hill School-Recreation Building: R
A02 057 Y N 7,804,680 7,804,680 1,697,440 1,697,440 22% 22% 6,107,240
40000400 - Minor Works Preservation Projects: State
A05 057 Y N 19,110 19,110 4,406 4,406 23% 23% 14,704
40000532 - Minor Works Preservation Projects - SW 2
C01 042 Y N 739,000 739,000 739,000
40000534 - Green Hill School - Baker North Remodel
C03 057 Y N 5,730,950 5,730,950 1,893,809 1,893,809 33% 33% 3,837,141
40000546 - Echo Glen Secure Facility Improvements
D02 057 N N 12,554,000 3,515,000 102,213 102,213 0.81% 0.81% 3,412,787
40000547 - Echo Glen Emergency Generator & Fuel Storage Tank
D00 057 N N 2,630,000 1,632,500 16,512 16,512 0.62% 0.62% 1,615,988
40000552 - Green Hill Spruce Living Unit Renovation Minimum Security
D01 057 N N 1,270,000 1,270,000 1,270,000
40000557 - Statewide Minor Works
D03 057 N N 2,959,000 1,249,500 40,275 40,275 1% 1% 1,209,225
40000584 - Green Hill School HVAC Upgrades
D04 26C N N 3,449,000
D05 057 N N 1,997,000
Totals 5,446,000 6,371,716
40000586 - Echo Glen Academic School Walkway Roofing & Lighting
D06 057 N N 500,000
307 - Department of Children, Youth, and Families Totals 43,550,600 25,858,600 6,371,716 148% 148% 19,486,884%