353 - Washington State Center for Childhood Deafness and Hearing Loss

Last Updated: 04/04/2024

Through March 2024

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000036 - Academic and Physical Education Building
C01 057 Y N 43,780,350 29,561,744 17,775,888 17,775,888 41% 41% 11,785,856
D00 057 N N 12,453,000
Totals 56,233,350 29,561,744 17,775,888 17,775,888 41% 41% 11,785,856%
30000047 - Minor Works: Preservation 2021-23
C00 057 Y N 75,000 1,920 1,920 3% 3% (1,920)
40000006 - Northrop Primary School Building Renovation
D01 057 N N 2,100,000 406,100 144,901 144,901 7% 7% 261,199
40000007 - 2023-25 Minor Works
D02 057 N N 830,000 235,000 235,000
353 - Washington State Center for Childhood Deafness and Hearing Loss Totals 59,238,350 30,202,844 17,922,709 50% 50% 12,280,135%