10-year project plan by agency

Washington State Center for Childhood Deafness and Hearing Loss

Major Function,
Agency, Project
Estimate
Total
Prior
Expenditures
Reapprop.
2023-25
New
Approp.
2023-25
Estimated
New
Approp.
2025-27
Estimated
New
Approp.
2027-29
Estimated
New
Approp.
2029-31
Estimated
New
Approp.
2031-33
40000007

23-25 Minor Works

State Building Construction Account - State
830,000 -- -- 830,000 -- -- -- --
30000036

Academic and Physical Education Building

State Building Construction Account - State
67,529,000 17,943,000 37,133,000 12,453,000 -- -- -- --
30000047

Minor Works: Preservation 2021-23

State Building Construction Account - State
245,000 -- 245,000 -- -- -- -- --
40000006

Northrop Primary School Building Renovation

State Building Construction Account - State
12,442,000 -- -- 12,442,000 -- -- -- --
Washington State Center for Childhood Deafness and Hearing Loss Fund Summary
State Building Construction Account - State 81,046,000 17,943,000 37,378,000 25,725,000 -- -- -- --