10-year project plan by county – statewide

Grays Harbor County

Project ID
Project Title
Estimate
Total
Prior
Expenditures
Reapprop.
2025-27
New Approp.
2025-27
Estimated
New
Approp.
2027-29
Estimated
New
Approp.
2029-31
Estimated
New
Approp.
2031-33
Estimated
New
Approp.
2033-35
310 - Department of Corrections
30001128

SCCC Roof Replacement

6,194,000 385,000 5,809,000 -- -- -- -- --
40000431

SCCC: Q-Bldg. Kitchen Floor Replacement

1,500,000 -- -- -- -- 1,500,000 -- --
Total for Department of Corrections 7,694,000 385,000 5,809,000 -- -- 1,500,000 -- --
461 - Department of Ecology
92000200

North Shore Levee

18,500,000 114,000 18,386,000 -- -- -- -- --
465 - State Parks and Recreation Commission
30001027

Ocean City Entrance Road Renovation

450,000 -- -- -- -- -- -- 450,000
40000236

Analyde Gap OBA Restroom and Site Improvements

500,000 -- -- -- -- -- -- 500,000
40000272

Grayland Beach Utility Upgrade

350,000 -- -- -- -- -- -- 350,000
40000273

Griffiths-Priday New Restroom and Trail

900,000 -- -- -- -- -- -- 900,000
40000285

Lake Sylvia Campground Improvements

300,000 -- -- -- -- -- -- 300,000
40000286

Lake Sylvia Dam Compliance

950,000 -- -- -- -- -- 950,000 --
40000287

Lake Sylvia Day Use Improvements

300,000 -- -- -- -- -- -- 300,000
40000288

Lake Sylvia Pavilion Parking Lot

350,000 -- -- -- -- -- -- 350,000
40000296

Ocean City Day Use Improvements

850,000 -- -- -- -- -- -- 850,000
40000297

Oyehut OBA Day Use Improvements

850,000 -- -- -- -- -- -- 850,000
40000299

Pacific Beach Reinforce Bulkhead

500,000 -- -- -- -- -- -- 500,000
40000300

Pacific Beach Replace Comfort Station

650,000 -- -- -- -- -- -- 650,000
40000306

Schafer Cabins

950,000 -- -- -- -- 950,000 -- --
40000307

Schafer Day Use Area Improvements

2,800,000 -- -- -- -- -- 2,800,000 --
40000308

Schafer Renovate West Campground

4,000,000 -- -- -- -- -- 2,000,000 2,000,000
40000313

Westport Light Trail Expansion and Connections

500,000 -- -- -- -- -- 500,000 --
40000314

Westport Light Westhaven Improvements

1,500,000 -- -- -- -- -- 1,500,000 --
40000428

Schafer Trailer Dump Station

800,000 -- -- -- -- 200,000 600,000 --
40000430

Westport Light Replace Restroom

750,000 -- -- -- -- -- 750,000 --
40000460

Twin Harbors South Beach Area Admin and Maint Facility

6,579,000 -- -- 1,366,000 5,213,000 -- -- --
Total for State Parks and Recreation Commission 24,829,000 -- -- 1,366,000 5,213,000 1,150,000 9,100,000 8,000,000
477 - Department of Fish and Wildlife
30000600

Humptulips Hatchery Renovate Ponds

15,250,000 -- -- -- -- 250,000 2,000,000 13,000,000
30000721

Mayr Brothers Hatchery - Intake Replacement

2,573,000 -- -- -- -- -- 600,000 1,973,000
Total for Department of Fish and Wildlife 17,823,000 -- -- -- -- 250,000 2,600,000 14,973,000
699 - Community and Technical College System
30000127

Grays Harbor College: Student Services and Instructional Building

48,177,000 47,559,000 618,000 -- -- -- -- --
40001150

Grays Harbor College: Lake Swano Dam

1,000,000 -- -- 1,000,000 -- -- -- --
Total for Community and Technical College System 49,177,000 47,559,000 618,000 1,000,000 -- -- -- --
Grays Harbor County Total 118,023,000 48,058,000 24,813,000 2,366,000 5,213,000 2,900,000 11,700,000 22,973,000