Twelfth Legislative District
| Project ID Project Title |
Estimate Total |
Prior Expenditures |
Reapprop. 2025-27 |
New Approp. 2025-27 |
Estimated New Approp. 2027-29 |
Estimated New Approp. 2029-31 |
Estimated New Approp. 2031-33 |
Estimated New Approp. 2033-35 |
|---|---|---|---|---|---|---|---|---|
| 225 Washington State Patrol | ||||||||
| 40000077 Fire Training Academy Roof Replacement |
572,000 | 290,000 | 282,000 | -- | -- | -- | -- | -- |
| 40000091 Fire Training Academy (FTA) Maintenance Building Roof Replacement |
300,000 | -- | -- | 300,000 | -- | -- | -- | -- |
| 40000092 Fire Training Academy (FTA) Fuel Farm Refurbishment |
1,000,000 | -- | -- | 1,000,000 | -- | -- | -- | -- |
| Total for 225 Washington State Patrol | 1,872,000 | 290,000 | 282,000 | 1,300,000 | -- | -- | -- | -- |
| 245 Military Department | ||||||||
| 30000592 King County Area Readiness Center |
13,055,000 | 6,488,000 | 6,567,000 | -- | -- | -- | -- | -- |
| 310 Department of Corrections | ||||||||
| 30000738 MCC: TRU Roof Programs and Recreation Building |
5,996,000 | 2,670,000 | 3,326,000 | -- | -- | -- | -- | -- |
| 365 Washington State University | ||||||||
| 40000376 Wenatchee Tree Fruit Research & Ext. Center Plant Growth Facility |
10,000,000 | -- | -- | 10,000,000 | -- | -- | -- | -- |
| 461 Department of Ecology | ||||||||
| 40000629 2025-27 Cleanup Settlement Account Projects |
650,000 | -- | -- | 650,000 | -- | -- | -- | -- |
| 465 State Parks and Recreation Commission | ||||||||
| 30000416 Lake Chelan State Park Moorage Dock Pile Replacement |
2,367,000 | 2,317,000 | 50,000 | -- | -- | -- | -- | -- |
| 30000731 Sun Lakes Relocate Shop Complex |
1,802,000 | -- | -- | -- | -- | 250,000 | 1,552,000 | -- |
| 40000066 Twenty-Five Mile Creek - Replace Moorage Floats |
1,867,000 | -- | -- | -- | 1,867,000 | -- | -- | -- |
| 40000069 Alta Lake - Major Park Renovation |
10,000,000 | -- | -- | -- | -- | -- | 600,000 | 9,400,000 |
| 40000156 Sun Lakes - Dry Falls Visitor's Center Renovation |
6,382,000 | -- | -- | 6,382,000 | -- | -- | -- | -- |
| 40000191 Lake Chelan Day Use Irrigation Renovation |
1,068,000 | -- | -- | -- | -- | 1,068,000 | -- | -- |
| 40000210 Lake Wenatchee South Campground Development |
3,443,000 | -- | -- | -- | -- | 722,000 | 1,573,000 | 1,148,000 |
| 40000216 Twenty-Five Mile Creek Irrigation Main Replacement |
2,011,000 | -- | -- | -- | -- | 401,000 | 1,610,000 | -- |
| 40000227 Lake Chelan Paving |
150,000 | -- | -- | -- | -- | -- | 150,000 | -- |
| 40000228 Lake Chelan Renovate Western Campground |
1,750,000 | -- | -- | -- | -- | 450,000 | 1,300,000 | -- |
| 40000229 Lincoln Rock Renovate Camploops #1 |
2,500,000 | -- | -- | -- | -- | 500,000 | 2,000,000 | -- |
| 40000338 Palouse to Cascades Trail Tekoa Trailhead |
600,000 | -- | -- | -- | -- | -- | -- | 600,000 |
| 40000350 Twenty-Five Mile Creek Replace Restroom |
250,000 | -- | -- | -- | -- | 250,000 | -- | -- |
| Total for 465 State Parks and Recreation Commission | 34,190,000 | 2,317,000 | 50,000 | 6,382,000 | 1,867,000 | 3,641,000 | 8,785,000 | 11,148,000 |
| 477 Department of Fish and Wildlife | ||||||||
| 30000828 Chelan Hatchery Renovation |
14,895,000 | -- | -- | -- | -- | -- | 1,700,000 | 13,195,000 |
| 699 Community and Technical College System | ||||||||
| 40000198 Wenatchee: Center for Technical Education and Innovation |
51,453,000 | 3,244,000 | 48,209,000 | -- | -- | -- | -- | -- |
| 40000593 Wenatchee: Immersive Technology & Engineering Center |
22,021,000 | -- | -- | -- | -- | 22,021,000 | -- | -- |
| Total for 699 Community and Technical College System | 73,474,000 | 3,244,000 | 48,209,000 | -- | -- | 22,021,000 | -- | -- |
| Total for Twelfth Legislative District | 154,132,000 | 15,009,000 | 58,434,000 | 18,332,000 | 1,867,000 | 25,662,000 | 10,485,000 | 24,343,000 |