Eastern Washington University

Science Renovation

30000549

Student enrollment at Eastern Washington University has exceeded the capacity of the current available science facilities and is unable to meet demands without additional science laboratory space. Funding is provided for the design phase to renovate an existing science building. The renovation will modernize and correct deficiencies in a 1960s era building, and expand class lab and research space to meet enrollment growth projections.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 7,937,000 103,838,000 111,775,000
Funds: State Building Construction Account - State 111,775,000

Minor Works: Preservation 2019-21

40000011

Funding is provided for minor capital projects to preserve and extend the life of existing campus facilities and their supporting infrastructure systems.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 6,500,000 0 6,500,000
Funds: Eastern Washington University Capital Projects Account - State 6,500,000

Minor Works: Program 2019-21

40000015

Funding is provided for minor capital programmatic work to modernize and renew existing space to improve functionality and program delivery.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 2,500,000 0 2,500,000
Funds: Eastern Washington University Capital Projects Account - State 2,500,000

Infrastructure Renewal II

40000016

Funding is provided for design and construction to upgrade Eastern Washington University’s Rozell Plant infrastructure. This project will address central steam production, chilled water production, medium voltage electrical distribution, and water resource needs and deficiencies. These infrastructure systems are mission critical components to Eastern’s primary goal of student success.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 20,000,000 0 20,000,000
Funds: State Building Construction Account - State 20,000,000

Preventative Maintenance/Backlog Reduction

40000017

Funding is provided to reduce the facilities maintenance backlog, extend the life cycle of equipment and systems, and reduce the maintenance and operating costs of facilities. This project will address high-priority issues that are of high cost and critical need on the campus and reduce the university's facility maintenance backlog.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 2,217,000 8,868,000 11,085,000
Funds: Eastern Washington University Capital Projects Account - State 11,085,000

Albers Court Improvements

40000036

The Physical Therapy program at Eastern Washington University lacks sufficient and adequate class and lab space. Currently, classes are taking place in space originally constructed as storage rooms. Spaces are isolated from other program classrooms and crowded because spaces are too small, and have inadequate ventilation. Funding is provided to enclose and finish Albers Court to create needed class and laboratory space.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 4,953,000 0 4,953,000
Funds: State Building Construction Account - State 4,953,000