Department of Fish and Wildlife
Migratory Waterfowl Habitat
20082045
State law mandates the Department of Fish and Wildlife to protect waterfowl and waterfowl habitat. This project provides authority to acquire threatened waterfowl habitat, enhance wildlife areas and fund projects on private lands to maintain and enhance waterfowl and wetlands habitats in Washington state.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
1,288,000 | 100,000 | 500,000 | 600,000 | 1,800,000 | 4,288,000 |
Funds: State Wildlife Account - State | 4,288,000 |
Mitigation Projects and Dedicated Funding
20082048
This project provides spending authority to use federal, private, local and special wildlife account monies received by the Department of Fish and Wildlife for dedicated conservation efforts and construction projects to increase recreational opportunities; repair or replace facilities or infrastructure; and provide restoration and long-term protection of critical fish and wildlife habitats.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
65,571,000 | 5,250,000 | 14,500,000 | 13,500,000 | 58,500,000 | 157,321,000 |
Funds: General Fund - Federal | 126,590,000 |
Funds: General Fund - Local | 7,994,000 |
Funds: State Wildlife Account - State | 7,529,000 |
Funds: Special Wildlife Account - Federal | 6,079,000 |
Funds: Special Wildlife Account - Local | 9,129,000 |
Eells Spring Hatchery Renovation
30000214
Eells Springs Hatchery is the largest trout producing facility in the Department of Fish and Wildlife hatchery system. Funding is provided for design and construction to renovate the hatchery based on the comprehensive predesign completed in June 2016. The renovation will ensure lowland recreational trout fishery opportunities in Mason, Thurston and Pierce Counties, and accommodate the Rainbow Trout production that will be shifted from Puyallup Hatchery. Reappropriation funding is also included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
93,000 | 10,000 | 1,390,000 | 10,262,000 | 1,400,000 | 13,155,000 |
Funds: State Building Construction Account - State | 13,155,000 |
Samish Hatchery Intakes
30000276
The current intake and fishway at Samish Hatchery do not meet current federal and state fish screen or fish passage criteria. Funding is provided to rebuild the Samish River intake at Samish Hatchery to comply with federal and state requirements, and improve native fish populations throughout the Samish River basin. Reappropriation funding is also included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
350,000 | 160,000 | 190,000 | 8,086,000 | 0 | 8,786,000 |
Funds: State Building Construction Account - State | 8,786,000 |
Minter Hatchery Intakes
30000277
Funding is provided to construct the gravity and pumped intakes for the Minter Creek Hatchery to make them compliant with current federal and state fish screening and fish passage criteria. Funding was provided during the 2015-17 biennium to develop a comprehensive predesign plan for Minter Hatchery intakes, and during the 2017-19 biennium to construct replacement water intakes as developed in the recently completed predesign plans. Reappropriation funding is also included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
104,000 | 301,000 | 6,200,000 | 2,427,000 | 0 | 9,032,000 |
Funds: State Building Construction Account - State | 9,032,000 |
Wooten Wildlife Area Improve Flood Plain
30000481
Funding is provided to improve conditions within the Tucannon floodplain, which will also serve as match capital funding for improvements to lakes with federal funds to improve conditions within the floodplain. The project will enhance both recreational opportunities and habitat for Endangered Species Act listed fish.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
966,000 | 4,484,000 | 150,000 | 1,500,000 | 6,000,000 | 13,100,000 |
Funds: General Fund - Federal | 4,600,000 |
Funds: State Building Construction Account - State | 8,500,000 |
Wallace River Hatchery - Replace Intakes and Ponds
30000660
The Wallace River Hatchery is located between the Wallace River and May Creek, both tributaries to Skykomish River. Funding is provided to rebuild the Wallace River intake and pollution abatement facilities at Wallace River Hatchery to comply with current fish passage and fish screening requirements, and clean water quality standards. This project also includes the hatchery building and public restrooms. Design and permit funding were provided in the 2017-19 biennium. Reappropriation funding is also included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 601,000 | 1,400,000 | 12,425,000 | 10,000,000 | 24,426,000 |
Funds: State Building Construction Account - State | 24,426,000 |
Soos Creek Hatchery Renovation
30000661
The Soos Creek Hatchery is an aging facility located in the floodplain and is damaged frequently by flooding events, putting staff at risk and creating large costly cleanups. Funding for Phase 1 was provided in the 2017-19 biennium and its reappropriation is included in this budget. Funding is provided for Phase 2 to construct a new hatchery incubation building that will be fed with settled water to enhance survival of incubating eggs and fry. Phase 2 will also rebuild the hatchery's water supply intake and pollution abatement systems to meet federal and state fish passage and fish screening criteria and water quality standards, as well as relocate the facilities out of the floodplain.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
3,000 | 5,697,000 | 6,000,000 | 4,831,000 | 3,031,000 | 19,562,000 |
Funds: State Building Construction Account - State | 19,562,000 |
Cooperative Elk Damage Fencing
30000662
Funding is provided for cooperative deer and elk damage prevention fencing through a cost share program with private landowners statewide. This funding will also replace over five miles of elk control fence on Washington Department of Fish and Wildlife property where the posts are rotten and the woven wire is brittle. This will prevent private crop damage and allow for sustaining the elk herds at population objectives identified in herd management plans.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 550,000 | 650,000 | 1,200,000 | 4,800,000 | 7,200,000 |
Funds: State Building Construction Account - State | 7,200,000 |
Spokane Hatchery Renovation
30000663
The Spokane Hatchery, located on the Little Spokane River, was constructed in 1934 and is outdated and in poor condition. Funding is provided to complete the predesign for the renovation of the facility that includes water intake and supply lines, the hatchery building, an office and storage building, rearing ponds and drain lines, fish protection netting facilities, pollution abatement facilities, and residences for staff assigned standby duty to ensure hatchery flows are maintained. Design, permitting and construction will occur the following biennium.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 150,000 | 13,788,000 | 13,938,000 |
Funds: State Building Construction Account - State | 13,938,000 |
Hazard Fuel Reductions, Forest Health and Ecosystem Improvement
30000665
Funding is provided to reduce severe wildfire risk and increase forest resiliency through fuels reduction, thinning, fuel break creation and prescribed burning up to 9,000 acres of treatments on Department of Fish and Wildlife lands. This project will improve habitat quality and reduce the risks to life and property due to wildfires.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 3,500,000 | 1,500,000 | 4,000,000 | 24,000,000 | 33,000,000 |
Funds: State Building Construction Account - State | 33,000,000 |
Naselle Hatchery Renovation
30000671
Funding is provided to continue the design and construction of the water intakes from the Naselle River to make them compliant with current federal and state fish screening and fish passage criteria, including the renovation of the Naselle Hatchery to maintain hatchery production into the Naselle River and the Willapa Bay Basin. Funding was provided in the 2015-17 biennium to develop a comprehensive predesign plan for Minter Hatchery intakes and in the 2017-19 biennium to start the design and construction. Reappropriation funding is also included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
132,000 | 300,000 | 7,700,000 | 14,220,000 | 28,220,000 | 50,572,000 |
Funds: State Building Construction Account - State | 50,572,000 |
Beaver Creek Hatchery - Renovation
30000680
The Beaver Creek Hatchery is failing. Funding is provided for predesign to replace the existing rearing ponds and water distribution box; replace and upgrade incubation room piping; and replace valves, incubation units, water supply and drain lines to continue salmonid production in the future. The Beaver Creek rearing programs support the lower Columbia River commercial tangle net fisheries, marked selective recreational fisheries in the main stem lower Columbia River, and the off-channel commercial fishery in Deep River. Design, permitting and construction will occur the following biennium.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 150,000 | 17,899,000 | 18,049,000 |
Funds: State Building Construction Account - State | 18,049,000 |
Snow Creek Reconstruct Facility
30000826
Reappropriation funding is provided for predesign to reconstruct the Snow Creek Resort facilities, including the launch, boarding floats, mooring floats, mooring buoys, accessible restrooms, campsites, water intake, water system, septic system and electrical service.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 75,000 | 25,000 | 150,000 | 4,794,000 | 5,044,000 |
Funds: State Building Construction Account - State | 5,044,000 |
Forks Creek Hatchery - Renovate Intake and Diversion
30000827
Funding is provided to remove and improve fish passage barriers; improve stream habitat by removing in-stream structures and adding large, woody debris; and upgrade Forks Creek Hatchery to current state and federal standards for fish passage and screening criteria. This project will open 28 miles of spawning and rearing habitat for Chum, Chinook and Coho salmon, Steelhead and Cutthroat Trout. Reappropriation is also included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 2,000 | 2,423,000 | 3,248,000 | 0 | 5,673,000 |
Funds: State Building Construction Account - State | 5,673,000 |
Hurd Creek - Relocate Facilities out of Floodplain
30000830
Recent changes in the Dungeness River channel have put the Hurd Creek Hatchery at high risk for hatchery produced salmon loss. Hurd Creek is a critical rearing facility integrated into the Puget Sound Recovery Chinook Recovery Plan. This facility is currently supplied with pathogen free water and Dungeness River Basin water, and utilized for the incubation and early rearing for both Dungeness River Chinook and Elwha River Chinook. Both stocks are identified as critical stocks for recovery in the Puget Sound. Funding is provided to relocate Hurd Creek facilities to higher ground due to flooding. The Office of Financial Management must approve the predesign before construction funds are allotted. Reappropriation is included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 200,000 | 600,000 | 12,435,000 | 0 | 13,235,000 |
Funds: State Building Construction Account - State | 13,235,000 |
Dungeness Hatchery - Replace Main Intake
30000844
The Dungeness River has been identified as a watershed of importance with its unique Chinook stocks and is essential for Puget Sound recovery. Funding is provided to upgrade the Dungeness Hatchery main intake to comply with new federal standards for fish passage and screening. Reappropriation is included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 315,000 | 300,000 | 5,084,000 | 0 | 5,699,000 |
Funds: State Building Construction Account - State | 5,699,000 |
PSNERP Match
30000846
Funding is provided for the federal and state share of costs for the ecosystem-based estuary restoration projects at three sites: Duckabush Estuary, North Fork Skagit River Delta and Nooksack River Delta as identified by the Puget Sound Nearshore Ecosystem Restoration Project (PSNERP). This project will be implemented in partnership with the Army Corps of Engineers over the next 10-18 years. Reappropriation is included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 9,000 | 1,491,000 | 7,778,000 | 424,426,000 | 433,704,000 |
Funds: General Fund - Federal | 263,223,000 |
Funds: State Building Construction Account - State | 170,481,000 |
Kalama Falls Hatchery Replace Raceways and PA System
30000848
Funding is provided to renovate the Kalama Falls Hatchery's raceways and replace the pollution abatement pond to meet current fish rearing guidelines and water quality standards. Reappropriation is also included from design funding that was provided in the 2017-19 biennium.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 66,000 | 750,000 | 6,800,000 | 6,800,000 | 14,416,000 |
Funds: State Building Construction Account - State | 14,416,000 |
Minor Works Preservation 2019-21
40000007
Funding is provided to repair or replace structures and infrastructure statewide that are critical to protecting state assets, preventing lawsuits and fines, and reducing the deferred maintenance backlog.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 9,030,000 | 0 | 9,030,000 |
Funds: State Building Construction Account - State | 9,030,000 |
Minor Works Programmatic 2019-21
40000008
Funding is provided to construct minor works programmatic projects statewide.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 2,927,000 | 0 | 2,927,000 |
Funds: State Building Construction Account - State | 2,927,000 |
Automated Salmon Marking Trailers
40000009
The Department of Fish and Wildlife is required by state law (RCW 77.95.290) to mass mark all hatchery Chinook and Coho destined for harvest in order to maintain the ability to provide commercial, tribal and recreational salmon fisheries while protecting native salmonid runs. Funding is provided to replace a portion of mass marking manual trailers with a more efficient method to ensure that all fish intended for harvest are mass marked.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 3,099,000 | 0 | 3,099,000 |
Funds: Certificate of Participation - State | 3,099,000 |
Toutle River Fish Collection Facility - Match
40000021
With the eruption of Mount St. Helens in 1980, the U.S. Army Corps of Engineers (Corps) constructed a sediment dam to manage sediments in the North Fork Toutle River to protect downstream communities. The dam limits fish passage for Endangered Species Act listed Coho and steelhead to historic spawning habitat in the Toutle River watershed. As mitigation, the Corps built a Fish Collection Facility to collect and transport adult fish to release sites upstream of the dam. Funding is provided for state match for the Corps funding to modify the Toutle River Fish Collection Facility to meet a 95 percent fish passage requirement. Funding also includes real property and easement acquisition to meet the state's obligation under the Local Cooperative Agreement, and funding for wildlife habitat mitigation associated with the planned raise of the Sediment Retention Structure.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 6,775,000 | 18,312,000 | 25,087,000 |
Funds: State Building Construction Account - State | 25,087,000 |
Elochoman Hatchery Demolition and Restoration
40000024
Expenditure authority is provided for federal funds to address the Elochoman Hatchery Demolition and restoration project.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 250,000 | 250,000 | 500,000 |
Funds: General Fund - Federal | 500,000 |
Infrastructure Master Plan for SRKW Recovery
40000085
Funding is provided for a master planning process that will assess existing Department of Fish and Wildlife hatchery infrastructure, determine needs and prioritize projects to support the recovery of the Southern Resident Killer Whales (SRKW).
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 1,000,000 | 0 | 1,000,000 |
Funds: State Building Construction Account - State | 1,000,000 |
Region 1 Office - Construct Secure Storage
40000087
Funding is provided to construct parking and storage areas for the Department of Fish and Wildlife's Region 1 Office in Spokane.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 150,000 | 6,329,000 | 6,479,000 |
Funds: State Building Construction Account - State | 6,479,000 |