Community and Technical College System

Wenatchee Valley: Wells Hall Replacement

30000985

Funding is provided to demolish and replace approximately two thirds of Wells Hall on the Wenatchee campus with a modern classroom and student support services building. The ceramics/theater wing will become a freestanding structure. Reappropriation funding is also included.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 32,000 2,808,000 34,531,000 0 37,371,000
Funds: State Building Construction Account - State 32,371,000
Funds: Institutions of Higher Education - Plant Accounts - Non-Appr 500,000
Funds: Certificate of Participation - State 4,500,000

Olympic: Shop Building Renovation

30000986

Funding is provided to renovate the Shop Building on the Bremerton Campus. Funding is also provided to add new space in the building for a new elevator that will provide accessibility to the second floor in accordance with the Americans with Disabilities Act, and program space for the Computer Numeric Control and Precision machinery program. Reappropriation funding is also included.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 4,000 949,000 7,652,000 0 8,605,000
Funds: State Building Construction Account - State 8,605,000

Pierce Fort Steilacoom: Cascade Building Renovation - Phase 3

30000987

Funding is provided for a partial renovation of the Cascade Building built in 1973. The renovation supports programs such as Dental Hygiene and Veterinary Technology. The project will also improve or add space for classrooms, the lecture hall, circulation areas and infrastructure and life safety systems. Reappropriation funding is also included.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 169,000 3,339,000 31,592,000 0 35,100,000
Funds: State Building Construction Account - State 35,100,000

South Seattle: Automotive Technology Renovation and Expansion

30000988

Funding is provided to renovate the Automotive Technology Building to correct inefficiencies and infrastructure deficiencies, and infill an existing service courtyard with a new two-story addition to address the shortfall of functional space.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 487,000 2,014,000 23,876,000 0 26,377,000
Funds: State Building Construction Account - State 25,877,000
Funds: Institutions of Higher Education - Plant Accounts - Non-Appr 500,000

Bates: Medical Mile Health Science Center

30000989

Funding is provided to replace the West Annex building at the Downtown Tacoma Campus with a new Medical Mile Health Science Center. The center will provide space for Allied Health and Science Technology Engineering and Math (STEM) programs, and include classroom and lab space. Reappropriation funding is also included.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 47,000 3,191,000 40,828,000 0 44,066,000
Funds: State Building Construction Account - State 44,066,000

Shoreline: Allied Health, Science & Manufacturing Replacement

30000990

Funding is provided to replace 64,615 gross square feet in five existing buildings with a single building to support the Science, Medical Laboratory Technology, Dental Hygiene and Manufacturing programs. Reappropriation funding is also included.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 584,000 3,008,000 39,642,000 0 43,234,000
Funds: State Building Construction Account - State 40,234,000
Funds: Institutions of Higher Education - Plant Accounts - Non-Appr 3,000,000

Yakima COP for West Campus Expansion

40000003

Provide additional instructional and lab space for high demand Allied Health programs. Also create a large meeting space to provide opportunities for collaborative interaction with faculty, staff and the community.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 22,700,000 0 22,700,000
Funds: Certificate of Participation - State 22,700,000

Preventive Facility Maintenance and Building System Repairs

40000043

Funding is provided to maintain and repair state-owned college and university facilities to optimize conditions for occupants and extend the useful life of the facilities.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 22,800,000 91,200,000 114,000,000
Funds: Community/Technical College Capital Projects Account - State 114,000,000

Lake Washington: Center for Design

40000102

Current facilities at the Lake Washington Institute of Technology do not support the needs of students, business partners and industry. A new building sized to accommodate growth and designed for creative and collaborative learning would address these shortfalls, and help the future the success of growing design and technology programs encompassing art, design, science, technology and engineering fields. Funding is provided for the predesign and design of a new building for design and technology programs.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 3,160,000 31,308,000 34,468,000
Funds: State Building Construction Account - State 34,468,000

Olympic Innovation and Technology Learning Center

40000103

Funding is provided for the predesign and design of a new Innovation and Technology Learning Center building. The building will include shared-use active learning classrooms, hand-on labs and student study space that will provide contemporary, high tech learning environments for a wide range of the college's STEM programs with tutoring and support services for K-12, veterans and military service students.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 2,552,000 21,703,000 24,255,000
Funds: State Building Construction Account - State 24,255,000

Minor Works - Program

40000112

Funding is provided for the ongoing need to renovate or upgrade program areas. The minor works projects ensure that college facilities remain suitable for student needs by meeting changing program requirements and providing an adequate educational environment.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 40,275,000 0 40,275,000
Funds: State Building Construction Account - State 39,841,000
Funds: Institutions of Higher Education - Plant Accounts - Non-Appr 434,000

Bates: Fire Service Training Center

40000130

The Bates Technical College Fire Service program prepares students for careers as fire fighters or in closely related occupations that require certification as a fire fighter. The current facilities are deficient in that they are too small and lack facilities required to support the program curriculum; live-training fire station facilities do not mirror the modern workplace; and the live-fire training yard does not have the necessary facilities for comprehensive training. Funding is provided for the predesign and design for a new fire training facility to ensure students can receive their certification without having to train offsite at other specialized facilities.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 2,802,000 30,000,000 32,802,000
Funds: State Building Construction Account - State 32,802,000

Bellevue: Center for Transdisciplinary Learning and Innovation

40000168

Funding is provided for the predesign and design of the Center for Transdisciplinary Learning and Innovation building. The new building will provide space for the information and business technologies (iBIT), computer science, interior design, art and engineering programs.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 2,839,000 38,476,000 41,315,000
Funds: State Building Construction Account - State 41,315,000

Facility Repairs

40000169

Funding is provided for high-priority building repairs identified in the latest Facility Condition Survey for community and technical colleges.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 38,527,000 0 38,527,000
Funds: State Building Construction Account - State 32,318,000
Funds: Community/Technical College Capital Projects Account - State 6,209,000

Roof Repairs

40000171

Funding is provided for high-priority roof repair or replacement projects identified in the latest Facility Condition Survey for community and technical colleges.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 15,252,000 0 15,252,000
Funds: Community/Technical College Capital Projects Account - State 15,252,000

Site Repairs

40000173

Funding is provided for high-priority site repair projects identified in the latest Facility Condition Survey for community and technical colleges.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 3,310,000 0 3,310,000
Funds: State Building Construction Account - State 3,310,000

Minor Works - Preservation

40000258

Funding is provided to establish an Emergency Reserve Fund for use by colleges with unforeseen capital repairs that exceed their financial capability and a Hazardous Material Fund for unanticipated abatement costs. Funds will also be used to perform the 2019 Facility Condition Survey to prioritize repair needs and assess facility conditions for future requests for 34 community and technical colleges.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 23,739,000 0 23,739,000
Funds: Community/Technical College Capital Projects Account - State 23,739,000

Pierce Puyallup: STEM building

40000293

Pierce College Puyallup lacks adequate and ample space to meet the current and growing needs of students and community, particularly in Science, Technology, Engineering and Math programs and support services. Funding is provided for the predesign and design of a new STEM building. The building will provide specialized spaces for several existing programs, flexible space for support classes, various unscheduled labs that support programs, and student study spaces, and will enable the expansion of critical support services in vacated space created by the project.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 3,369,000 37,230,000 40,599,000
Funds: State Building Construction Account - State 40,599,000

COP for Columbia Basin Student Recreation Center

40000301

Authority is granted for Columbia Basin College to enter into a financing agreement to construct a student recreation center. The debt service, operation and maintenance will come from student fees.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 30,000,000 0 30,000,000
Funds: Institutions of Higher Education - Plant Accounts - Non-Appr 3,000,000
Funds: Certificate of Participation - State 27,000,000

COP for Pierce Puyallup Parking Expansion

40000302

Authority is granted for Pierce College Puyallup to enter into a financing agreement to purchase real property and construct a parking lot to serve the students of the college. The debt service, operation and maintenance will come from student fees.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 3,956,000 0 3,956,000
Funds: Institutions of Higher Education - Plant Accounts - Non-Appr 1,125,000
Funds: Certificate of Participation - State 2,831,000

COP for Walla Walla main campus Student Recreation Center

40000303

Authority is granted for Walla Walla College to enter into a financing agreement to construct a student recreation center. The debt service, operation and maintenance will come from student fees.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 8,000,000 0 8,000,000
Funds: Institutions of Higher Education - Plant Accounts - Non-Appr 1,500,000
Funds: Certificate of Participation - State 6,500,000

COP for Walla Walla Clarkston campus Student Activity Center

40000304

Authority is granted for Walla Walla College to renovate approximately 2,800 gross square feet of space for use as a student activity center on the Clarkston campus. The debit service, operation and maintenance will come from student fees.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 1,750,000 0 1,750,000
Funds: Institutions of Higher Education - Plant Accounts - Non-Appr 250,000
Funds: Certificate of Participation - State 1,500,000

2019-21 Career Preparation and Launch Equipment Grants

40000306

Funding is provided for competitive grants to community and technical colleges to purchase and install equipment that expand Career Connected Learning opportunities.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 10,500,000 42,000,000 52,500,000
Funds: State Building Construction Account - State 52,500,000