245 - Military Department
Last Updated: 01/16/2026
Through January 2026
| Auth Code | Fund | Reapprop | Provisos | Current Biennium Appropriation | Budgeted Cost of Work (Allotted) | Actual Cost of Work | Outstanding Contracting Balance (Encumbered) | Total Dollars Obligated | Percent Obligated | Percent Expended | Biennium to Date Variance (Allotted - Actuals) | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| This Month | Biennium to Date | This Month | Biennium to Date | ||||||||||
| 30000591 - Joint Force Readiness Center: Replacement | |||||||||||||
| D00 | 057 | Y | N | 11,556,743 | 937,500 | 962,218 | 962,218 | 8.32% | 8.32% | (24,718) | |||
| Q00 | 001 | Y | N | 42,000,000 | 2,812,500 | 2,812,500 | |||||||
| Totals | 53,556,743 | 3,750,000 | 962,218 | 962,218 | 1.8% | 1.8% | 2,787,782 | ||||||
| 30000592 - King County Area Readiness Center | |||||||||||||
| D02 | 057 | Y | N | 6,545,454 | 32,619 | 32,619 | 0.49% | 0.49% | (32,619) | ||||
| 30000808 - Tri-Cities Readiness Center | |||||||||||||
| D05 | 057 | Y | N | 333,818 | 334,000 | 5,851 | 5,851 | 1.75% | 1.75% | 328,149 | |||
| L00 | 001 | Y | N | 927,484 | |||||||||
| Totals | 1,261,302 | 334,000 | 1,000,688 | 5,851 | 0.46% | 0.46% | 328,149 | ||||||
| 30000930 - Snohomish Readiness Center | |||||||||||||
| D07 | 057 | Y | N | 2,269,514 | 1,932,420 | 1,604,112 | 1,604,112 | 70.68% | 70.68% | 328,308 | |||
| Q06 | 001 | Y | N | 6,119,565 | 5,290,797 | 2,845,845 | 2,845,845 | 46.5% | 46.5% | 2,444,952 | |||
| Totals | 8,389,079 | 7,223,217 | 5,450,645 | 4,449,957 | 53.04% | 53.04% | 2,773,260 | ||||||
| 40000004 - Anacortes Readiness Center Major Renovation | |||||||||||||
| A06 | 364 | Y | N | 18,575 | 18,718 | 18,718 | |||||||
| C02 | 057 | Y | N | 151,239 | 152,000 | 95 | 95 | 0.06% | 0.06% | 151,905 | |||
| N03 | 001 | Y | N | 366,468 | 367,000 | 367,000 | |||||||
| Totals | 536,282 | 537,718 | 5,450,740 | 95 | 0.02% | 0.02% | 537,623 | ||||||
| 40000073 - Stryker Canopies Kent Site | |||||||||||||
| L05 | 001 | Y | N | 1,167,000 | |||||||||
| 40000077 - Stryker Canopies Bremerton Site | |||||||||||||
| L06 | 001 | Y | N | 332,858 | 333,000 | 1,909 | 1,909 | 0.57% | 0.57% | 331,091 | |||
| 40000104 - Field Maintenance Shop Addition-Sedro Woolley FMS | |||||||||||||
| Q08 | 001 | Y | N | 504,167 | 504,143 | 92 | 92 | 0.01% | 0.01% | 504,051 | |||
| 40000191 - Camp Murray Bldg 65 Barracks Replacement | |||||||||||||
| Q11 | 001 | Y | N | 2,195,000 | 2,066,914 | 189,484 | 189,484 | 8.63% | 8.63% | 1,877,430 | |||
| 40000192 - Camp Murray Bldg 34 Renovation | |||||||||||||
| D09 | 057 | Y | N | 4,428,344 | 3,176,320 | 242,598 | 242,598 | 5.47% | 5.47% | 2,933,722 | |||
| Q12 | 001 | Y | N | 5,221,404 | 3,745,469 | 284,789 | 284,789 | 5.45% | 5.45% | 3,460,680 | |||
| Totals | 9,649,748 | 6,921,789 | 6,169,612 | 527,387 | 5.47% | 5.47% | 6,394,402 | ||||||
| 40000194 - Moses Lake Readiness Center Renovation | |||||||||||||
| D10 | 057 | Y | N | 927,643 | 916,752 | 574,651 | 574,651 | 61.94% | 61.94% | 342,101 | |||
| E00 | 057 | N | N | 349,000 | 254,772 | 254,772 | |||||||
| Q13 | 001 | Y | N | 1,278,798 | 1,265,110 | 674,590 | 674,590 | 52.75% | 52.75% | 590,520 | |||
| Q31 | 001 | N | N | 576,000 | 420,480 | 420,480 | |||||||
| Totals | 3,131,441 | 2,857,114 | 7,418,853 | 1,249,241 | 39.89% | 39.89% | 1,607,873 | ||||||
| 40000196 - JBLM Non-Organizational (POV) Parking Expansion | |||||||||||||
| Q15 | 001 | Y | N | 1,317,219 | |||||||||
| 40000274 - Minor Works Program 2023-25 Biennium | |||||||||||||
| D11 | 057 | Y | N | 3,971,356 | 2,569,914 | 553,538 | 553,538 | 13.93% | 13.93% | 2,016,376 | |||
| Q16 | 001 | Y | N | 6,849,640 | 4,480,436 | 197,429 | 197,429 | 2.88% | 2.88% | 4,283,007 | |||
| Totals | 10,820,996 | 7,050,350 | 8,169,820 | 750,967 | 6.94% | 6.94% | 6,299,383 | ||||||
| 40000290 - WA Army National Guard Vehicle Storage Buildings | |||||||||||||
| D01 | 057 | Y | N | 750,000 | 615,000 | 615,000 | |||||||
| Q17 | 001 | Y | N | 10,953,519 | 192,702 | 161,241 | 161,241 | 1.47% | 1.47% | 31,461 | |||
| Totals | 11,703,519 | 807,702 | 8,331,061 | 161,241 | 1.38% | 1.38% | 646,461 | ||||||
| 40000297 - Yakima Training Center 951 Renovation | |||||||||||||
| Q19 | 001 | Y | N | 2,854,688 | 2,695,774 | 1,280 | 1,280 | 0.04% | 0.04% | 2,694,494 | |||
| 40000298 - Central Building Automation System for National Guard Buildings | |||||||||||||
| Q20 | 001 | Y | N | 2,227,000 | 2,100,764 | 2,100,764 | |||||||
| 40000300 - Spokane Readiness Center IT Infrastructure Upgrade | |||||||||||||
| D13 | 057 | Y | N | 131,177 | 140,600 | 140,600 | |||||||
| Q21 | 001 | Y | N | 379,520 | 402,500 | 402,500 | |||||||
| Totals | 510,697 | 543,100 | 8,332,341 | 543,100 | |||||||||
| 40000301 - Minor Works Preservation 2023-25 Biennium | |||||||||||||
| D12 | 057 | Y | N | 2,469,000 | 1,645,726 | 299,511 | 299,511 | 12.13% | 12.13% | 1,346,215 | |||
| Q22 | 001 | Y | N | 2,914,000 | 1,934,186 | 459,871 | 459,871 | 15.78% | 15.78% | 1,474,315 | |||
| Totals | 5,383,000 | 3,579,912 | 9,091,723 | 759,382 | 14.11% | 14.11% | 2,820,530 | ||||||
| 40000305 - Wenatchee Army National Guard Aviation Support Facility | |||||||||||||
| D14 | 364 | Y | N | 3,500,000 | |||||||||
| 40000311 - Kent Readiness Center Water Damage Repairs | |||||||||||||
| D16 | 057 | Y | N | 235,952 | 247,535 | 579 | 579 | 0.24% | 0.24% | 246,956 | |||
| Q02 | 001 | Y | N | 707,857 | 707,900 | 1,737 | 1,737 | 0.24% | 0.24% | 706,163 | |||
| Totals | 943,809 | 955,435 | 9,094,039 | 2,316 | 0.25% | 0.25% | 953,119 | ||||||
| 40000345 - Minor Works Program 2025-27 Biennium | |||||||||||||
| E01 | 057 | N | N | 1,441,000 | 942,782 | 942,782 | |||||||
| Q32 | 001 | N | N | 8,444,000 | 5,524,546 | 5,524,546 | |||||||
| Totals | 9,885,000 | 6,467,328 | 9,094,039 | 6,467,328 | |||||||||
| 40000346 - Minor Works Preservation 2025-27 Bienniu | |||||||||||||
| E02 | 057 | N | N | 5,751,000 | 3,762,635 | 3,762,635 | |||||||
| Q33 | 001 | N | N | 10,290,000 | 6,732,308 | 6,732,308 | |||||||
| Totals | 16,041,000 | 10,494,943 | 9,094,039 | 10,494,943 | |||||||||
| 40000347 - Camp Murray Mechanical Security Barricad | |||||||||||||
| Q34 | 001 | N | N | 2,660,000 | 944,780 | 944,780 | |||||||
| 40000348 - Joint Base Lewis-McChord Army Aviation S | |||||||||||||
| Q35 | 001 | N | N | 4,462,000 | 1,265,027 | 9,936 | 9,936 | 0.22% | 0.22% | 1,255,091 | |||
| 40000349 - Moses Lake Readiness Center Stormwater R | |||||||||||||
| E03 | 057 | N | N | 113,000 | 93,930 | 93,930 | |||||||
| Q36 | 001 | N | N | 113,000 | 93,930 | 93,930 | |||||||
| Totals | 226,000 | 187,860 | 9,103,975 | 187,860 | |||||||||
| 40000350 - Yakima Readiness Center Repairs | |||||||||||||
| E04 | 057 | N | N | 193,000 | |||||||||
| Q37 | 001 | N | N | 223,000 | |||||||||
| Totals | 416,000 | 9,103,975 | |||||||||||
| 40000351 - Yakima Training Center 960 (MATES) HVAC | |||||||||||||
| Q38 | 001 | N | N | 5,741,000 | 1,672,216 | 1,672,216 | |||||||
| 40000352 - Yakima Training Center Military Vehicle | |||||||||||||
| Q39 | 001 | N | N | 3,623,000 | 1,729,185 | 1,729,185 | |||||||
| 40000354 - Geiger Field 200 Restoration | |||||||||||||
| E05 | 057 | N | N | 436,000 | 193,776 | 193,776 | |||||||
| Q41 | 001 | N | N | 566,000 | 251,556 | 251,556 | |||||||
| Totals | 1,002,000 | 445,332 | 9,103,975 | 445,332 | |||||||||
| 40000356 - Geiger Field 402 Renovation | |||||||||||||
| E06 | 057 | N | N | 465,000 | 465,000 | 465,000 | |||||||
| Q42 | 001 | N | N | 537,000 | 537,000 | 537,000 | |||||||
| Totals | 1,002,000 | 1,002,000 | 9,103,975 | 1,002,000 | |||||||||
| 40000357 - Joint Base Lewis-McChord 9608 (UTES) Int | |||||||||||||
| Q43 | 001 | N | N | 782,000 | 570,858 | 570,858 | |||||||
| 40000359 - Longview Readiness Center Renovation | |||||||||||||
| E07 | 057 | N | N | 295,000 | 131,112 | 131,112 | |||||||
| Q44 | 001 | N | N | 399,000 | 177,332 | 177,332 | |||||||
| Totals | 694,000 | 308,444 | 9,103,975 | 308,444 | |||||||||
| 40000366 - Sedro Woolley Field Maintenance Shop Ren | |||||||||||||
| Q45 | 001 | N | N | 5,520,000 | 416,100 | 416,100 | |||||||
| 40000367 - Tumwater Field Maintenance Shop | |||||||||||||
| D17 | 057 | Y | N | 480,000 | 393,600 | 379,128 | 379,128 | 78.98% | 78.98% | 14,472 | |||
| E08 | 057 | N | N | 3,700,000 | |||||||||
| Q24 | 001 | Y | N | 3,900,000 | |||||||||
| Totals | 8,080,000 | 393,600 | 9,483,103 | 379,128 | 4.69% | 4.69% | 14,472 | ||||||
| 40000368 - Yakima Readiness Center Deep Energy Retr | |||||||||||||
| E09 | 057 | N | N | 78,000 | |||||||||
| Q46 | 001 | N | N | 205,000 | |||||||||
| Totals | 283,000 | 9,483,103 | |||||||||||
| 40000369 - Yakima Training Center (MATES) Renovatio | |||||||||||||
| Q47 | 001 | N | N | 7,950,000 | 547,500 | 547,500 | |||||||
| 40000403 - Redmond Readiness Center (500 and 501) R | |||||||||||||
| E10 | 057 | N | N | 127,000 | |||||||||
| Q48 | 001 | N | N | 649,000 | |||||||||
| Totals | 776,000 | 9,483,103 | |||||||||||
| 245 - Military Department Totals | 195,673,002 | 68,706,105 | 9,483,103 | 9,483,103 | 4.85% | 4.85% | 59,223,002 | ||||||