Capital Budgeted Expenditures

351 - State School For The Blind

Last Updated: 10/28/2026

Through October 2026

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
40000021 - 2023-25 Campus Preservation (Minor Works)
D00 057 Y N 567,546 900,000 552,324 552,324 97.31% 97.31% 347,676
40000054 - Dormitory Modernization
E00 057 N N 350,000 50,000 50,000 8,350 40,417 40,417 11.54% 11.54% 9,583
40000060 - Minor works projects 2025-27
E01 057 N N 2,110,000 130,000 1,245,000 12,336 324,303 324,303 15.36% 15.36% 920,697
351 - State School For The Blind Totals 3,027,546 180,000 2,195,000 20,686 917,044 917,044 30.29% 30.29% 1,277,956