Capital Budgeted Expenditures

395 - Eastern Washington State Historical Society

Last Updated: 01/16/2026

Through January 2026

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
Unknown
057 N N 20,000
40000017 - Campbell and Carriage House Repairs and Restoration
C01 057 Y N 476,153 648,000 89,937 89,937 18.88% 18.88% 558,063
40000053 - Garage & Emergency Exit Concrete Remediation
C05 057 Y N 835,426 1,783,000 170,811 170,811 20.44% 20.44% 1,612,189
40000054 - Minor Works: Preservation 2023-25
D00 057 Y N 791,745 800,000 86,895 86,895 10.97% 10.97% 713,105
40000064 - Museum Expansion and Modernization
E00 057 N N 600,000 600,000 89,762 89,762 14.96% 14.96% 510,238
395 - Eastern Washington State Historical Society Totals 2,723,324 3,831,000 437,405 437,405 16.06% 16.06% 3,393,595