Skip to Main content
Agency detail budgets – current law

Toll Operations and Maintenance - Department of Transportation

Request 172,889,000
Net change from current biennium 82,065,786 Increase
Percent change from current biennium 90.4% Increase

Program Level Summary

Fund Title Actual Estimated Proposed
2022-23 Actual 2023-24 Estimated 2024-25 Estimated 2025-26 Proposed 2026-27 Proposed
State Route Number 520 Corridor Account - State 20,209,928 24,418,037 6,690,971 23,620,000 24,056,000
State Route Number 520 Civil Penalties Account - State 394,853 1,049,878 482,725 1,196,000 1,182,000
Puget Sound Gateway Facility Account - State 2,995,000 4,656,000
Tacoma Narrows Toll Bridge Account - State 15,502,346 16,787,901 8,280,278 19,119,000 19,439,000
Alaskan Way Viaduct Replacement Project Account - State 9,134,491 11,272,971 4,932,030 13,099,000 13,479,000
Interstate 405 and State Route Number 167 Express Toll Lanes Account - State 9,535,417 12,016,716 4,891,707 24,566,000 25,482,000
Annual Total 54,777,035 65,545,503 25,277,712 84,595,000 88,294,000

Operating Budget: Change from Preceding Biennium

2021-23 Actual 2023-25 Estimated 2025-27 Proposed
Amount Percent Amount Percent Amount Percent
(3,350,846) (3.1%) (14,398,383) (13.7%) 82,065,786 90.4%