Whatcom Community College: Learning Commons

30000138

Funding is adjusted to reflect lapsed expenditure authority.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
95,000 (5,396,000) (5,301,000)
State Building Construction Account - State (5,301,000)

Spokane: Main Building South Wing Renovation

30000982

Funding is adjusted to reflect lapsed expenditure authority.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
(126,000) (126,000)
State Building Construction Account - State (126,000)

Bates: Medical Mile Health Science Center

30000989

Funding has been adjusted to reflect expenditures.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
(101,000) 101,000
State Building Construction Account - State

CBPS SBCTC Statewide: Utility Submeters for Clean Buildings Act

40000878

Over 60% of state community and technical college buildings lack utility submeters that collect baseline energy data and meet Clean Buildings Performance Standards. This project funds installation of utility submeters for qualifying buildings, allowing collection of energy consumption information and establish the required energy use intensity.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
8,544,000 8,544,000
Community/Technical College Capital Projects Account - State 170,000
Climate Commitment Account - State 8,374,000

CTC Energy Efficiency Program

40000880

Funds retro-commission of aging and underperforming building systems, ensuring they run at their optimal performance. Retro-commissioning projects improve energy efficiency, extend equipment life, reduce greenhouse gas emissions and operating expenses. The board will allocate funds to colleges through a competitive selection process.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
2,000,000 2,000,000
Climate Commitment Account - State 2,000,000

COP for Renton Technical College Building J Renovations

40000881

Funding is provided to upgrade computer classrooms on the 1st floor of Building J. Renovations will improve circulation and daylight access, address space and capacity needs, modernize finishes and relocate faculty offices.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
2,000,000 2,000,000
Certificate of Participation - Non-Appr 2,000,000

Bellingham Technical College: Campus Center Building

40000916

Funding is provided for seismic and load work on the Campus Center Building.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
19,384,000 19,384,000
State Building Construction Account - State 19,384,000

HB 1390 - District Energy Systems

91000443

Funding is provided to support implementation of 2SHB 1390 District Energy Systems.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
724,000 724,000
Climate Commitment Account - State 724,000