Skip to Main content
Capital Budgeted Expenditures

360 - University of Washington

Last Updated: 10/08/2025

Through September 2025

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
20091002 - UW Anderson Hall Renovation
D00 057 Y N 15,171,000 15,171,000 56,729 56,729 0.37% 0.37% 15,114,271
R13 148 Y N 11,950,000
Totals 27,121,000 15,171,000 56,729 56,729 0.21% 0.21% 15,114,271
30000378 - UW Bothell
A01 057 Y N 1,263,000 1,263,000 1,263,000
30000808 - UW Major Infrastructure
D01 064 Y N 6,577,000 6,577,000 186,783 186,783 2.83% 2.83% 6,390,217
E00 064 N N 10,300,000 4,223,000 4,223,000
Totals 16,877,000 10,800,000 243,512 186,783 1.11% 1.11% 10,613,217
40000049 - Magnuson Health Sciences Phase II
D03 057 Y N 35,457,000 32,785,839 5,809,349 5,809,349 16.38% 16.38% 26,976,490
40000049 - Magnuson Health Sciences Phase II - Renovation/Replacement
R12 148 Y N 2,100,000
40000098 - UW Clean Energy Testbeds
D04 26C Y N 2,501,000 1,667,328 590,761 590,761 23.62% 23.62% 1,076,567
40000100 - Intellectual House - Phase 2
D05 057 Y N 8,978,000 4,688,590 199 199 0% 0% 4,688,391
R11 148 Y N 6,300,000
Totals 15,278,000 4,688,590 6,643,821 199 0% 0% 4,688,391
40000101 - UW Tacoma - Land Acquisition
D06 057 Y N 4,199,000 4,199,000 418,000 418,000 9.95% 9.95% 3,781,000
40000103 - UW Seattle - Asset Preservation (Minor Works) 23-25
D07 064 Y N 19,044,000 9,522,000 1,066,458 1,066,458 5.59% 5.59% 8,455,542
40000129 - UW Bothell - Asset Preservation (Minor Works) 23-25
D08 064 Y N 2,096,000 1,047,996 136,744 136,744 6.52% 6.52% 911,252
40000131 - UW Tacoma - Asset Preservation (Minor Works) 23-25
D09 064 Y N 1,407,000 703,500 32,772 32,772 2.32% 2.32% 670,728
40000132 - Infrastructure Renewal
D10 064 Y N 8,499,000 4,249,500 406,316 406,316 4.78% 4.78% 3,843,184
D11 26C Y N 6,296,000 3,147,996 693,290 693,290 11.01% 11.01% 2,454,706
Totals 14,795,000 7,397,496 9,397,401 1,099,606 7.43% 7.43% 6,297,890
40000146 - Chemical Sciences & Bagley Hall
D02 057 Y N 5,000,000 5,000,000 163,464 163,464 3.26% 3.26% 4,836,536
E01 057 N N 124,000,000 15,400,000 15,400,000
R10 148 Y N 61,000,000
Totals 190,000,000 20,400,000 9,560,865 163,464 0.09% 0.09% 20,236,536
40000147 - Energy Renewal Program
D15 26C Y N 38,900,000 19,449,996 217 217 0% 0% 19,449,779
40000159 - Infrastructure Renewal 25-27
E02 064 N N 39,350,000 19,674,996 19,674,996
40000160 - UW Tacoma - Campus Power Repairs (Phase
E03 064 N N 3,900,000 1,950,000 1,950,000
40000161 - UW Bothell - Asset Preservation (Minor W
E04 064 N N 4,530,000 2,265,000 2,265,000
40000163 - UW Seattle - Asset Preservation (Minor W
E05 064 N N 22,080,000 11,040,000 276,805 276,805 1.25% 1.25% 10,763,195
40000164 - UW Tacoma - Asset Preservation (Minor Wo
E06 064 N N 5,415,000 2,707,500 6,692 6,692 0.12% 0.12% 2,700,808
91000016 - Ctr for Advanced Materials and Clean Ene
R14 148 Y N 263,100,000
U75 057 Y N 11,533,000 2,250,000 6,098 6,098 0.05% 0.05% 2,243,902
Totals 274,633,000 2,250,000 9,850,677 6,098 0% 0% 2,243,902
91000027 - UWMC NW - Campus Behavioral Health Renovation
D12 057 Y N 5,822,000 5,822,000 29,966 29,966 0.51% 0.51% 5,792,034
91000029 - Preventive Facility Maintenance and Building System Repairs
E08 064 N N 25,825,000 12,912,504 12,912,504
92000002 - UW Tacoma Campus Soil Remediation
D14 23N Y N 3,953,000 976,500 83,245 83,245 2.1% 2.1% 893,255
92000014 - FIFA World Cup Improvements
E07 057 N N 1,700,000 1,700,000 1,700,000
360 - University of Washington Totals 758,246,000 190,394,245 9,963,888 9,963,888 1.31% 1.31% 180,430,357