Capital Budgeted Expenditures

370 - Eastern Washington University

Last Updated: 10/08/2025

Through September 2025

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
Unknown
057 N N (2,306) (2,306) 2,306
30000507 - Science Renovation
D00 057 Y N 52,089,000 3,359,909 3,359,909 6.45% 6.45% (3,359,909)
40000070 - Infrastructure Renewal III
C01 057 Y N 739,000 (1,824) (1,824) -0.24% -0.24% 1,824
40000112 - Sports and Recreation Center Energy Improvements
D07 26C Y N 9,998,000 5,797 5,797 0.05% 0.05% (5,797)
40000113 - Martin - Williamson Hall
D01 057 Y N 64,000 (501) (501) -0.78% -0.78% 501
40000114 - Infrastructure Renewal IV
D02 057 Y N 7,268,000 151,273 151,273 2.08% 2.08% (151,273)
40000116 - Minor Works: Preservation 2023-25
D03 057 Y N 2,843,000 240,378 240,378 8.45% 8.45% (240,378)
40000120 - Minor Works: Program 2023-25
D04 061 Y N 2,919,000 328,531 328,531 11.25% 11.25% (328,531)
40000157 - Dental Therapy Lab and Clinic
E00 057 N N 10,498,000
40000222 - Preventative Maintenance/Backlog Reducti
E01 061 N N 2,217,000 184,750 184,750 8.33% 8.33% (184,750)
91000027 - HB 1390 – District Energy Systems
D06 26C Y N 49,000
91000031 - 2025-27 Minor Works Preservation and Pro
E02 057 N N 6,000,000 617 617 0.01% 0.01% (617)
E03 061 N N 9,800,000 23,089 23,089 0.23% 0.23% (23,089)
Totals 15,800,000 4,289,713 23,706 0.15% 0.15% (23,706)
370 - Eastern Washington University Totals 104,484,000 4,289,713 4,289,713 4.11% 4.11% (4,289,713)