Fourth Legislative District
| Project ID Project Title |
Estimate Total |
Prior Expenditures |
Reapprop. 2025-27 |
New Approp. 2025-27 |
Estimated New Approp. 2027-29 |
Estimated New Approp. 2029-31 |
Estimated New Approp. 2031-33 |
Estimated New Approp. 2033-35 |
|---|---|---|---|---|---|---|---|---|
| 245 Military Department | ||||||||
| 40000349 Moses Lake Readiness Center Stormwater Repairs |
1,094,000 | -- | -- | 113,000 | 981,000 | -- | -- | -- |
| 40000349 Moses Lake Readiness Center Stormwater Repairs |
1,094,000 | -- | -- | 113,000 | 981,000 | -- | -- | -- |
| 40000350 Yakima Readiness Center Repairs |
2,190,000 | -- | -- | 223,000 | 1,967,000 | -- | -- | -- |
| 40000350 Yakima Readiness Center Repairs |
1,733,000 | -- | -- | 193,000 | 1,540,000 | -- | -- | -- |
| 40000351 Yakima Training Center 960 (MATES) HVAC System Replacement |
5,741,000 | -- | -- | 5,741,000 | -- | -- | -- | -- |
| 40000352 Yakima Training Center Military Vehicle Parking Repair |
3,623,000 | -- | -- | 3,623,000 | -- | -- | -- | -- |
| 40000361 Pasco Readiness Center Restoration |
4,927,000 | -- | -- | -- | 4,927,000 | -- | -- | -- |
| 40000361 Pasco Readiness Center Restoration |
3,478,000 | -- | -- | -- | 3,478,000 | -- | -- | -- |
| 40000369 Yakima Training Center (MATES) Renovation |
7,950,000 | -- | -- | 7,950,000 | -- | -- | -- | -- |
| Total for 245 Military Department | 31,830,000 | -- | -- | 17,956,000 | 13,874,000 | -- | -- | -- |
| 465 State Parks and Recreation Commission | ||||||||
| 30000959 Mount Spokane - Maintenance Facility Relocation from Harms Way |
2,610,000 | 2,360,000 | 250,000 | -- | -- | -- | -- | -- |
| 30000982 Mount Spokane Road Improvements Stage 3 Linders - Snowblaze |
5,042,000 | -- | -- | 938,000 | 4,104,000 | -- | -- | -- |
| 40000054 Mount Spokane - Nordic Area Improvements & Horse Camp Development |
4,900,000 | -- | -- | -- | -- | 800,000 | 4,100,000 | -- |
| 40000441 Mount Spokane New Chair Lift |
4,146,000 | -- | -- | -- | -- | -- | 4,146,000 | -- |
| 40000446 Centennial Trail Paving Repair and Overlay Phase 3 |
2,000,000 | -- | -- | -- | -- | 2,000,000 | -- | -- |
| Total for 465 State Parks and Recreation Commission | 18,698,000 | 2,360,000 | 250,000 | 938,000 | 4,104,000 | 2,800,000 | 8,246,000 | -- |
| 477 Department of Fish and Wildlife | ||||||||
| 40000087 Region 1 Office - Construct Secure Storage |
150,000 | 94,000 | 56,000 | -- | -- | -- | -- | -- |
| Total for Fourth Legislative District | 50,678,000 | 2,454,000 | 306,000 | 18,894,000 | 17,978,000 | 2,800,000 | 8,246,000 | -- |