Capital Budgeted Expenditures

350 - Superintendent of Public Instruction

Last Updated: 10/08/2025

Through September 2025

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000169 - 2015-17 School Construction Assistance Program
T93 113 Y N 672,000 100 92 92 0.01% 100
30000197 - Tri-Tech Skill Center - Core Growth
U89 057 Y N 4,000
40000003 - 2017-19 School Construction Assistance Program
C19 057 Y N 10,000
U19 113 Y N 6,229,000 31,600 96,445 96,445 1.54% 31,600
Totals 6,239,000 31,600 96,445 96,445 1.55% 31,600
40000013 - 2019-21 School Construction Assistance Program
A00 057 Y N 41,000
A01 113 Y N 22,129,000 4,013,913 97,223 16,359,470 16,456,693 74.36% 0.43% 3,916,690
Totals 22,170,000 4,013,913 97,223 16,359,470 16,456,693 74.23% 0.44% 3,916,690
40000015 - West Sound Technical Skills Center Modernization
D32 113 Y N 27,734,000 10,470,200 5,489,002 4,981,222 10,470,224 37.75% 19.79% 4,981,198
E19 057 N N 42,000,000
Totals 69,734,000 10,470,200 5,586,225 4,981,222 10,470,224 15.01% 7.87% 4,981,198
40000019 - School District Health and Safety 2019-21
A06 057 Y N 101,000
40000023 - Skills Centers Minor Works
A09 057 Y N 216,000
40000034 - 2021-23 School Construction Assistance Program
C01 057 Y N 59,449,000 26,496,000 488,485 52,512,369 53,000,854 89.15% 0.82% 26,007,515
C02 113 Y N 8,488,000 1,553,515 246,007 2,299,071 2,545,078 29.98% 2.89% 1,307,508
N01 113 Y N 2,207,000
Totals 70,144,000 28,049,515 6,320,717 54,811,440 55,545,932 79.19% 1.05% 27,315,023
40000039 - 2021-23 Small District and Tribal Compact Schools Modernization
C05 057 Y N 2,874,000 1,788,600 1,788,558 1,788,558 62.23% 1,788,600
40000040 - 2021-23 Skills Centers Minor Works
C06 057 Y N 876,000 332,700 332,700 332,700 37.97% 332,700
40000048 - Pierce County Skills Center - Evergreen Building Modernization
C07 057 Y N 1,348,000 840,200 840,156 840,156 62.32% 840,200
40000050 - Seattle Public Schools Skills Center - Rainier Beach High School
C08 057 Y N 300,000 300,000 300,000 300,000 100% 300,000
40000051 - Puget Sound Skills Center Preservation
C09 057 Y N 345,000 345,000 345,106 345,106 100.03% 345,000
40000052 - 2021-23 School District Health and Safety
C10 113 Y N 134,000
C11 057 Y N 476,000
Totals 610,000 6,320,717
40000056 - 2021-23 Career Preparation and Launch Grants
C13 113 Y N 161,000 63,300 22,922 36,488 59,410 36.9% 14.23% 40,378
40000063 - 2023-25 School Construction Assistance Program
D02 113 Y N 172,370,000 63,800,500 182,732 169,907,883 170,090,615 98.67% 0.1% 63,617,768
D03 057 Y N 11,352,000
Q02 113 Y N 1,500,000
Totals 185,222,000 63,800,500 6,526,371 169,907,883 170,090,615 91.83% 0.1% 63,617,768
40000065 - 2023-25 Small District & Tribal Compact Schools Modernization
D07 26C Y N 3,630,000 1,116,600 111,940 111,940 3.08% 3.08% 1,004,660
D09 113 Y N 128,368,000 48,965,300 15,726,982 7,769,247 23,496,229 18.3% 12.25% 33,238,318
D10 057 Y N 10,717,000 9,445,000 9,826,526 9,826,526 91.69% 9,445,000
Totals 142,715,000 59,526,900 22,365,293 17,595,773 33,434,695 23.43% 11.1% 43,687,978
40000066 - 2023-25 School Seismic Safety Grant Program
D14 057 Y N 40,000,000 25,652,400 3,780,319 21,872,184 25,652,503 64.13% 9.45% 21,872,081
40000067 - 2023-25 School District Health and Safety
D34 113 Y N 14,208,000 4,915,500 846,350 1,098,795 1,945,145 13.69% 5.95% 4,069,150
40000068 - 2023-25 Healthy Kids-Healthy Schools
D19 113 Y N 4,434,000 1,546,500 375,903 375,903 8.47% 8.47% 1,170,597
D20 057 Y N 422,000 325,800 5,791 4,518 10,309 2.44% 1.37% 320,009
Totals 4,856,000 1,872,300 27,373,656 4,518 386,212 7.95% 7.86% 1,490,606
40000069 - 2023-25 Career Preparation and Launch Capital Grants
D23 113 Y N 1,178,000 379,000 80,790 80,790 6.85% 6.85% 298,210
40000070 - 2023-25 Skills Centers Minor Works
D38 113 Y N 2,912,000 2,485,500 162,475 2,322,953 2,485,428 85.35% 5.57% 2,323,025
40000099 - Chief Leschi School HVAC
D27 057 Y N 819,000
40000104 - School District Indoor Air Quality & Energy Efficiency
D39 113 Y N 14,472,000 1,645,500 85,537 85,537 0.59% 0.59% 1,559,963
D40 26C Y N 30,000,000 1,680,000 1,680,000
Totals 44,472,000 3,325,500 27,702,458 85,537 0.19% 0.19% 3,239,963
40000142 - 2025-27 K-12 Capital Programs Administra
E00 113 N N 6,312,000 2,968,562 266,325 266,325 4.21% 4.21% 2,702,237
40000143 - 2025-27 School Inventory & Condition Dat
E01 057 N N 1,360,000
40000144 - Air Quality Improvement Grants (>3,000 enrollments)
E20 26C N Y 5,568,000
E21 057 N Y 2,273,000
Totals 7,841,000 27,968,783
40000144 - Air Quality Improvement Grants (<3,000 enrollments)
E22 26C N Y 6,932,000
E23 057 N Y 2,727,000
Totals 9,659,000 27,968,783
40000146 - Emergency Repair Grants
E35 057 N Y 11,000,000 8,000 7,481 405,450 412,931 3.75% 0.06% 519
40000146 - Urgent Repair Grants
E37 057 N Y 15,000,000
40000146 - Equal Access Grants
E38 057 N Y 5,000,000
40000147 - Healthy Kids-Healthy Schools Grant
E24 113 N Y 12,000,000
40000147 - Drinking Water Fixture Replacements
E25 113 N Y 1,000,000
40000148 - 2025-27 Career Preparation and Launch Gr
E06 113 N N 4,000,000
40000150 - 2025-27 Small District and STEC Schools
E08 113 N N 530,000
40000150 - Modernization Grants-Small Districts
E26 057 N Y 174,450,000
40000150 - Modernization Grants-State Tribal Compacts
E27 057 N Y 27,371,000 306,668 24,644,332 24,951,000 91.15% 1.12% (306,668)
40000153 - 2025-27 School Construction Assistance P
E09 057 N N 425,065,000 40,557,000 40,557,000
E10 113 N N 3,007,000 1,003,000 458,337 458,337 15.24% 1,003,000
Q31 113 N N 1,500,000 750,000 750,000
Totals 429,572,000 42,310,000 28,282,932 458,337 458,337 0.11% 42,310,000
40000158 - 2025-27 Skills Center Minor Works
E11 057 N N 5,818,000 1,164,400 2,724,200 2,724,200 46.82% 1,164,400
40000159 - 2025-27 School Seismic Safety Grant Prog
E12 057 N N 151,451,000 79,617,800 11,406,022 129,778,368 141,184,390 93.22% 7.53% 68,211,778
91000464 - 2021-23 Healthy Kids-Healthy Schools: Physical Health & Nutrition
C03 113 Y N 220,000
91000465 - 2021-23 Healthy Kids-Healthy Schools: Remediation of Lead
C14 113 Y N 270,000 134,400 134,400
C15 057 Y N 2,965,000 1,891,300 1,891,297 1,891,297 63.78% 1,891,300
Totals 3,235,000 2,025,700 39,688,954 1,891,297 1,891,297 58.46% 2,025,700
91000466 - Green Schools: Stormwater Infrastructure Projects
D28 23R Y N 263,000 263,000 263,000
91000483 - Healthy Kids/Healthy Schools - T-12 Lighting
C38 057 Y N 1,361,000
91000509 - Energy Assessment Grants to School Districts
D47 26C Y N 4,900,000 2,801,900 2,801,913 2,801,913 57.18% 2,801,900
D48 113 Y N 50,000 50,000 50,000
Totals 4,950,000 2,851,900 39,688,954 2,801,913 2,801,913 56.6% 2,851,900
91000519 - School-based Health and Behavioral Health Clinics
D51 057 Y N 1,864,000 885,500 301,879 301,879 16.19% 885,500
91000534 - Career and Technical Education Projects
D52 113 Y N 65,735,000 64,635,900 12,050 64,623,876 64,635,926 98.32% 0.01% 64,623,850
91000535 - School Construction Assistance Program Revision (SCAPR) Planning
D53 113 Y N 1,000,000 437,500 437,500
91002551 - SCAPR Transitional Projects
E13 057 N N 6,000,000 4,800,000 6,000,000 6,000,000 100% 4,800,000
91002551 - Pe Ell K-12 Modernization
E32 113 N Y 8,131,000 3,600,000 5,303,014 5,303,014 65.21% 3,600,000
91002551 - Bridgeport Elementary School Modernization
E33 113 N Y 6,000,000 3,600,000 6,000,000 6,000,000 100% 3,600,000
91002551 - Inchelium K-12 Modernization
E34 113 N Y 3,972,000
92000036 - Pierce College at New Bethel High School
C46 057 Y N 1,600,000
92000039 - K-3 Class-size Reduction Grants
T38 057 Y N 3,224,000 127,900 177,963 177,963 5.51% 127,900
92000041 - Distressed Schools
U56 057 Y N 143,000 143,000 143,446 143,446 100.31% 143,000
92000139 - 2019-21 Small District Modernization Grants
A11 057 Y N 176,000 11,500 11,533 11,533 6.55% 11,500
92000140 - 2019-21 STEM Grants
A12 057 Y N 4,000
92000142 - 2019-21 Distressed Schools
A13 057 Y N 784,000 431,900 431,857 431,857 55.08% 431,900
92000148 - 2019-21 School Seismic Safety Retrofit Program
A02 057 Y N 1,545,000 1,049,700 287,525 762,193 1,049,718 67.94% 18.61% 762,175
92000917 - 2021-23 Distressed Schools
C18 057 Y N 8,734,000 8,572,900 724 8,572,122 8,572,846 98.15% 0.01% 8,572,176
92000923 - 2021-23 School Seismic Safety Grant Program
C37 057 Y N 15,429,000 5,876,800 2,554,691 3,322,034 5,876,725 38.08% 16.55% 3,322,109
92000925 - 2022 Small District and Tribal Compact Schools Modernization
C45 057 Y N 84,000
92000928 - 2023-25 Distressed Schools
D30 057 Y N 21,132,000 1,290,800 2,918,227 2,918,227 13.8% 1,290,800
D54 113 Y N 8,941,000 5,265,500 714,138 7,364,118 8,078,256 90.35% 7.98% 4,551,362
Totals 30,073,000 6,556,300 43,258,082 10,282,345 10,996,483 36.57% 2.37% 5,842,162
92000931 - 2023-25 Agricultural Science in Schools Grant to FFA Foundation
D31 057 Y N 3,000
92001066 - 2024 School Construction Assistance Program Enhancement
D55 113 Y N 24,216,000 10,839,000 30,144 21,388,703 21,418,847 88.44% 0.12% 10,808,856
D56 057 Y N 55,000,000 12,422,000 267,648 26,760,978 27,028,626 49.14% 0.48% 12,154,352
Totals 79,216,000 23,261,000 43,555,874 48,149,681 48,447,473 61.16% 0.38% 22,963,208
92001915 - 2025-27 Distressed Schools
E16 23N N N 1,000,000
92001915 - Acme Elementary Modernization
E28 057 N Y 237,000
92001915 - Lawton Elementary School
E29 057 N Y 6,227,000
92001915 - Maritime 235: South Puget Sound Maritime Skills Center
E30 057 N Y 4,000,000
92001915 - TOPS K-8 School
E31 057 N Y 3,500,000
92001922 - 2025-27 Agricultural Science in Schools
E17 057 N N 5,150,000 2,575,000 2,575,000
92002069 - School Security and Preparedness Infrast
E18 057 N N 6,000,000
350 - Superintendent of Public Instruction Totals 1,744,400,000 465,966,990 43,555,874 609,479,623 653,035,497 37.44% 2.5% 422,411,116