353 - Washington State Center for Childhood Deafness and Hearing Loss

Last Updated: 07/07/2025

Through June 2025

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000036 - Academic and Physical Education Building
C01 057 Y N 43,780,350 (196,282) 43,976,642 (9,518,553) 43,778,784 43,778,784 100% 100% 197,858
D00 057 N N 12,453,000 1,032,628 12,422,896 9,791,139 9,791,139 9,791,139 79% 79% 2,631,757
Totals 56,233,350 836,346 56,399,538 272,586 53,569,923 53,569,923 179% 179% 2,829,615%
30000047 - Minor Works: Preservation 2021-23
C00 057 Y N 75,000 75,000 (287,358) 65,566 65,566 87% 87% 9,434
40000006 - Northrop Primary School Building Renovation
D01 057 N N 2,100,000 96,743 1,365,217 10,677 1,225,785 1,225,785 58% 58% 139,432
40000007 - 2023-25 Minor Works
D02 057 N N 830,000 25,000 730,000 350,241 350,241 350,241 42% 42% 379,759
353 - Washington State Center for Childhood Deafness and Hearing Loss Totals 59,238,350 958,089 58,569,755 346,146 55,211,515 367% 367% 3,358,240%