370 - Eastern Washington University

Last Updated: 04/04/2024

Through March 2024

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000507 - Renovate Science
C00 057 Y N 15,858,770 15,858,770 11,536,762 11,536,762 73% 73% 4,322,008
30000507 - Science Renovation
D00 057 N N 58,000,000 12,000,000 12,000,000
40000016 - Infrastructure Renewal II
A03 057 Y N 4,406,130 4,406,130 4,245,653 4,245,653 96% 96% 160,477
40000070 - Infrastructure Renewal III
C01 057 Y N 8,882,980 6,750,000 4,251,705 4,251,705 48% 48% 2,498,295
40000071 - Lucy Covington Center
C02 061 Y N 237,660 225,000 71,001 71,001 30% 30% 153,999
40000107 - Minor Works: Preservation 2021-23
C03 061 Y N 988,490 988,490 879,359 879,359 89% 89% 109,131
40000112 - CBPS: Sports and Recreation Center Energy Improvements
D07 26C N N 9,998,000
40000113 - Martin - Williamson Hall
D01 057 N N 350,000 350,000 20,182 20,182 6% 6% 329,818
40000114 - Infrastructure Renewal IV
D02 057 N N 12,000,000 3,200,000 656,499 656,499 5% 5% 2,543,501
40000116 - Minor Works: Preservation 2023-25
D03 057 N N 5,375,000 2,700,000 261,210 261,210 5% 5% 2,438,790
40000120 - Minor Works: Program 2023-25
D04 061 N N 6,000,000 2,025,000 461,439 461,439 8% 8% 1,563,561
40000134 - Preventative Maintenance/Backlog Reduction
D05 061 N N 2,217,000 1,108,500 739,000 739,000 33% 33% 369,500
91000027 - HB 1390 – District Energy Systems
D06 26C N N 200,000 200,000 200,000
370 - Eastern Washington University Totals 124,514,030 49,811,890 23,122,810 393% 393% 26,689,080%