Home » Budget » Capital Budgeted Expenditures » 225 - Washington State Patrol

225 - Washington State Patrol

Last Updated: 01/07/2025

Through December 2024

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
WSP Transportation Capital Projects
D01 081 N Y 7,888,000 8,500 7,753,287 648,544 4,223,664 4,223,664 54% 54% 3,529,623
30000171 - FTA Emergency Power Generator Replacemen
C00 057 Y N 323,060 323,060 216,897 216,897 67% 67% 106,163
30000240 - Vancouver Crime Lab - New Roof
D02 057 N N 1,594,000 1,594,000 464,104 464,104 29% 29% 1,129,896
30000290 - Crime Laboratory I-5 North Corridor Consolidated Facility
D03 057 N N 42,000 42,000 42,000
D04 057 N N 7,200,000 120,000 6,360,000 2,079 42,546 42,546 0.59% 0.59% 6,317,454
Totals 7,242,000 120,000 6,402,000 2,079 4,947,211 42,546 0.59% 0.59% 6,359,454%
40000031 - FTA Minor Works and Repairs
D06 057 N N 237,000 9,900 168,300 234,359 234,359 99% 99% (66,059)
40000034 - FTA - Student Dormitory HVAC
C02 057 Y N 12,850 12,850 12,850
40000072 - Crime Laboratory South I-5 Corridor Consolidated Facility
D07 057 N N 8,600,000 350,000 4,765,000 3,234 206,014 206,014 2% 2% 4,558,986
40000077 - Fire Training Academy Roof Replacement
D08 057 N N 572,000 572,000 289,210 289,210 51% 51% 282,790
40000081 - Seattle Crime Laboratory Generator Replacement
D09 057 N N 450,000 450,000 450,000
225 - Washington State Patrol Totals 26,918,910 488,400 22,040,497 653,857 5,676,794 302% 302% 16,363,703%