365 - Washington State University

Last Updated: 07/07/2025

Through June 2025

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000840 - WSU Vancouver - Life Sciences Building
C00 057 Y N 11,173,750 11,173,750 11,173,750 11,173,750 100% 100%
40000012 - Spokane-Biomedical and Health Sc Buildin
C02 057 Y N 804,160 804,160 804,144 804,144 100% 100% 16
40000145 - Minor Capital Preservation (MCR): 2021-2
C03 062 Y N 1,660,900 1,660,900 663,401 1,660,900 1,660,900 100% 100%
40000272 - Campus Fire Protection and Domestic Wate
C06 057 Y N 85,070 85,070 85,069 85,069 100% 100% 1
40000274 - Clark Hall Research Lab Renovation
C07 062 Y N (80,373)
40000339 - Pullman Student Success Center Phase 1
C10 057 Y N 493,770 493,770 493,770 493,770 100% 100%
40000340 - Minor Capital Preservation 2023-25 (MCR)
D00 062 N N 40,000,000 2,650,000 36,000,000 1,978,687 34,729,448 34,729,448 87% 87% 1,270,552
D11 057 N N 1,000,000 25,000 975,000 71,553 484,279 484,279 48% 48% 490,721
Totals 41,000,000 2,675,000 36,975,000 2,050,240 49,431,360 35,213,727 135% 135% 1,761,273%
40000341 - Minor Capital Program 2023-25 (MCI & Omnibus Equip.)
D01 062 N N 6,500,000 500,000 6,000,000 100,893 5,680,889 5,680,889 87% 87% 319,111
D02 057 N N 6,500,000 650,000 6,000,000 170,607 5,792,453 5,792,453 89% 89% 207,547
Totals 13,000,000 1,150,000 12,000,000 271,500 60,904,702 11,473,342 177% 177% 526,658%
40000342 - New Engineering Student Success Building & Infrastructure
D03 057 N N 40,000,000 4,650,000 37,132,000 3,615,544 29,342,819 29,342,819 73% 73% 7,789,181
40000343 - Knott Dairy Infrastructure
D04 057 N N 10,000,000 50,000 10,000,000 794,175 9,824,348 9,824,348 98% 98% 175,652
40000344 - Bustad Renovation (SIM for Vet Teaching Anatomy)
D05 057 N N 8,000,000 8,000,000 250,037 7,246,094 7,246,094 91% 91% 753,906
40000346 - Clean Building Standard Energy Efficiency Improvements
D06 26C N N 5,000,000 100,000 4,950,000 4,986,969 4,986,969 100% 100% (36,969)
40000361 - Spokane Team Health Education Building
D07 057 N N 7,000,000 150,000 6,850,000 359,019 3,893,385 3,893,385 56% 56% 2,956,615
40000362 - Eastlick-Abelson Renovation
D08 057 N N 22,000,000 500,000 21,500,000 745,281 21,164,987 21,164,987 96% 96% 335,013
91000037 - Preventive Facility Maintenance and Building System Repairs
D10 062 N N 10,115,000 562,000 10,115,000 562,000 10,115,000 10,115,000 100% 100%
91000043 - Decarbonization Planning
D12 26C N N 3,000,000 1,500,000 2,400,000 70,429 237,741 237,741 8% 8% 2,162,259
92001125 - Agriculture Research Stations
D09 057 N N 1,000,000 1,000,000 766 951,082 951,082 95% 95% 48,918
92001132 - Knott Dairy Center Digester
D13 26C N N 10,000,000 4,500,000 7,000,000 3,000 650,234 650,234 7% 7% 6,349,766
365 - Washington State University Totals 184,332,650 15,837,000 172,139,650 9,305,019 149,317,361 1,535% 1,535% 22,822,289%