Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000002 - Creative Districts Capital Construction
C00 057 Y N 368,390 368,390 5,086 176,408 176,408 48% 48% 191,982
30000003 - 2023-25 Creative Districts Capital Projects Program
D00 057 N N 416,000 34,637 381,363 1,006 11,523 11,523 3% 3% 369,840
30000004 - Preserving State-owned Public Art
D01 057 N N 735,000 103,000 632,000 95,550 95,550 13% 13% 536,450
387 - Washington State Arts Commission Totals 1,519,390 137,637 1,381,753 6,092 283,481 64% 64% 1,098,272%