225 - Washington State Patrol

Last Updated: 08/26/2025

Through July 2025

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
WSP Transportation Capital Projects
D01 081 N Y 6,531,000 (1,352,500) 6,451,787 765,537 6,408,424 6,408,424 98% 98% 43,363
30000171 - FTA Emergency Power Generator Replacemen
C00 057 Y N 323,060 323,060 255,776 255,776 79% 79% 67,284
30000240 - Vancouver Crime Lab - New Roof
D02 057 N N 1,594,000 1,594,000 4,195 499,649 499,649 31% 31% 1,094,351
30000290 - Crime Laboratory I-5 North Corridor Consolidated Facility
D03 057 N N 42,000 42,000 42,000
D04 057 N N 7,200,000 120,000 7,200,000 4,789 73,714 73,714 1% 1% 7,126,286
Totals 7,242,000 120,000 7,242,000 4,789 7,237,563 73,714 1% 1% 7,168,286%
40000031 - FTA Minor Works and Repairs
D06 057 N N 237,000 9,300 237,000 234,359 234,359 99% 99% 2,641
40000034 - FTA - Student Dormitory HVAC
C02 057 Y N 12,850 12,850 12,850
40000072 - Crime Laboratory South I-5 Corridor Consolidated Facility
D07 057 N N 8,600,000 335,000 8,600,000 46,043 413,599 413,599 5% 5% 8,186,401
40000077 - Fire Training Academy Roof Replacement
D08 057 N N 572,000 572,000 289,307 289,307 51% 51% 282,693
40000081 - Seattle Crime Laboratory Generator Replacement
D09 057 N N 450,000 450,000 14,106 14,106 14,106 3% 3% 435,894
40000097 - Vancouver Crime Lab Chiller Replacement
D10 057 N N 988,000 988,000 988,000 988,000
225 - Washington State Patrol Totals 26,549,910 99,800 26,470,697 834,670 8,188,934 367% 367% 18,281,763%