You are here

Home » Budget » Budget-related information » Agency expenditure monitoring » Capital Budgeted Expenditures » 353 - Washington State Center for Childhood Deafness and Hearing Loss

353 - Washington State Center for Childhood Deafness and Hearing Loss

Last Updated: 08/26/2025

Through July 2025

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000036 - Academic and Physical Education Building
C01 057 Y N 43,780,350 (196,292) 43,780,350 43,778,784 43,778,784 100% 100% 1,566
D00 057 N N 12,453,000 30,104 12,453,000 612,657 10,403,795 10,403,795 84% 84% 2,049,205
Totals 56,233,350 (166,188) 56,233,350 612,657 54,182,579 54,182,579 184% 184% 2,050,771%
30000047 - Minor Works: Preservation 2021-23
C00 057 Y N 75,000 75,000 65,566 65,566 87% 87% 9,434
40000006 - Northrop Primary School Building Renovation
D01 057 N N 2,100,000 734,783 2,100,000 157,289 1,383,074 1,383,074 66% 66% 716,926
40000007 - 2023-25 Minor Works
D02 057 N N 830,000 100,000 830,000 323,118 673,359 673,359 81% 81% 156,641
353 - Washington State Center for Childhood Deafness and Hearing Loss Totals 59,238,350 668,595 59,238,350 1,093,064 56,304,578 418% 418% 2,933,772%