463 - Energy Facility Site Evaluation Council
Last Updated: 08/26/2025
Summary Financial Report for 2023-25 Biennium to Date
Dollars in thousands
All Funds Variance to Date
19,443 Underexpenditure
52.6% Underexpenditure
Planned vs. Actual Cumulative Expenditures - All Funds
Monthly Planned vs. Actual Expenditures - All Funds
Monthly Planned vs. Actual Expenditures - GFS
Expenditure by Program
Program | Estimate | Actual | Variance | % Variance |
---|---|---|---|---|
Administration | 36,967 | 17,524 | 19,443 | 52.6% |
Totals | 36,967 | 17,524 | 19,443 | 52.6% |
FTE
Program | Estimate | Actual | Variance | % Variance |
---|---|---|---|---|
Administration | 35 | 23 | 12 | 33.1% |
Totals | 35 | 23 | 12 | 33.1% |
Expenditure by Fund Group
Program | Estimate | Actual | Variance | % Variance |
---|---|---|---|---|
General Fund State | 2,633 | 2,310 | 323 | 12.3% |
Other Funds Private/Local | 26,897 | 11,377 | 15,520 | 57.7% |
Other Funds State | 7,437 | 3,837 | 3,600 | 48.4% |
Totals | 36,967 | 17,524 | 19,443 | 52.6% |
Revenue by Fund Group
Program | Estimate | Actual | Variance | % Variance |
---|---|---|---|---|
General Fund State | 4 | 4 | ||
Other Funds Private/Local | 26,897 | 9,249 | (17,648) | (65.6%) |
Other Funds State | 84 | 84 | ||
Totals | 26,897 | 9,337 | (17,560) | (65.3%) |
Revenue by Fund
Program | Estimate | Actual | Variance | % Variance |
---|---|---|---|---|
General Fund | 4 | 4 | ||
Climate Commitment Account | 53 | 53 | ||
Energy Facility Site Eval Council Acct | 26,897 | 9,280 | (17,617) | (65.5%) |
Totals | 26,897 | 9,337 | (17,560) | (65.3%) |
Deficit Fund Balance
Program | BTD Balance | Proj. Balance |
---|---|---|
Energy Facility Site Eval Council Acct | (2,154) | (2,154) |