2025 supplemental capital two-year agency detail - Military Department
Tri-Cities Readiness Center
30000808
Reappropriation of state funding and federal spending authority is provided to complete the construction closeout and art installation at the Tri-Cities Readiness Center.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
(2,700,000) | (2,700,000) |
General Fund - Federal | (2,000,000) |
State Building Construction Account - State | (700,000) |
Snohomish Readiness Center
30000930
Reappropriation of state funding and federal spending authority is provided to complete the renovation of the Snohomish Readiness Center.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
2,700,000 | 2,700,000 |
General Fund - Federal | 2,000,000 |
State Building Construction Account - State | 700,000 |
Tumwater Field Maintenance Shop
40000367
Funding is provided to design and construct a new Field Maintenance Shop in Tumwater.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
4,380,000 | 49,977,000 | 54,357,000 |
General Fund - Federal | 49,450,000 |
State Building Construction Account - State | 4,907,000 |