Capital Two-Year Agency Detail - Central Washington University
Secondary Geothermal Module
40000161
This project funds the engineering and construction of one injection and one extraction well, and the construction of a second GeoEco Plant to supplement the first GeoEco Plant being constructed at the North Academic Complex. The GeoEco plant will house all mechanical, electrical, and plumbing equipment associated with geothermal wells.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
12,464,000 | 4,000,000 | 16,464,000 |
Climate Commitment Account - State | 16,464,000 |
Science Building Carbon Reduction
40000162
Funding is provided for carbon reduction projects at the Science Building.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
4,509,000 | 4,509,000 |
Climate Commitment Account - State | 4,509,000 |