10-year project plan by agency

Washington State Center for Childhood Deafness and Hearing Loss

Major Function,
Agency, Project
Estimate
Total
Prior
Expenditures
Reapprop.
2025-27
New
Approp.
2025-27
Estimated
New
Approp.
2027-29
Estimated
New
Approp.
2029-31
Estimated
New
Approp.
2031-33
Estimated
New
Approp.
2033-35
40000012

2025-27 Minor Works

State Building Construction Account - State
2,125,000 -- -- 2,125,000 -- -- -- --
30000036

Academic and Physical Education Building

State Building Construction Account - State
67,529,000 65,129,000 2,400,000 -- -- -- -- --
40000006

Northrop Primary School Building Renovation

State Building Construction Account - State
18,262,000 1,600,000 500,000 16,162,000 -- -- -- --
Washington State Center for Childhood Deafness and Hearing Loss Fund Summary
State Building Construction Account - State 87,916,000 66,729,000 2,900,000 18,287,000 -- -- -- --
Total for Washington State Center for Childhood Deafness and Hearing Loss 87,916,000 66,729,000 2,900,000 18,287,000 -- -- -- --