Install subterranean and submarine power cable from Seattle City Light vault 5 at Pier 48 to Colman Dock slips 1 and 3. Complete construction of the trestle SW corner, install shoreside battery energy storage system and vessel charging system.
Methods for providing public comment for agency consideration as part of the environmental justice assessment.
WSFelectrification@WSDOT.WA.GOV
Link to agency webpage where the action is posted.
Status
Project location
Address
801 Alaskan Way, Seattle, WA 98104
Geolocation
Geolocation is 47.602304, -122.338315