You are here

Home » Seattle Ferry Terminal Electrification Project

Seattle Ferry Terminal Electrification Project

Agency
Transportation, Department of
Title of action
Seattle Ferry Terminal Electrification Project
Date significant agency action was initiated
Wednesday, November 15, 2023
Category
Transportation project, grant, or loan of at least $15 million
Brief description of significant agency actions for which the agency is initiating an environmental justice assessment.
Install subterranean and submarine power cable from Seattle City Light vault 5 at Pier 48 to Colman Dock slips 1 and 3. Complete construction of the trestle SW corner, install shoreside battery energy storage system and vessel charging system.
Methods for providing public comment for agency consideration as part of the environmental justice assessment.
WSFelectrification@WSDOT.WA.GOV
Status
Project location
Address
801 Alaskan Way, Seattle, WA 98104
Geolocation

Geolocation is 47.602304, -122.338315