Chelan County
Project ID Project Title |
Estimate Total | Prior Expenditures | Reapprop. 2023-25 | New Approp. 2023-25 | Estimated New Approp. 2025-27 | Estimated New Approp. 2027-29 | Estimated New Approp. 2029-31 | Estimated New Approp. 2031-33 |
---|---|---|---|---|---|---|---|---|
465 State Parks and Recreation Commission |
||||||||
30000416 Lake Chelan State Park Moorage Dock Pile Replacement |
2,418,000 | 1,772,000 | 72,000 | 574,000 | ||||
699 Community and Technical College System |
||||||||
30000985 Wenatchee Valley: Wells Hall Replacement |
32,371,000 | 29,259,000 | 3,112,000 | |||||
40000198 Wenatchee: Center for Technical Education and Innovation |
49,737,000 | 986,000 | 2,280,000 | 46,471,000 | ||||
Total for Community and Technical College System | 82,108,000 | 30,245,000 | 5,392,000 | 46,471,000 | ||||
Chelan County Total | 84,526,000 | 32,017,000 | 5,464,000 |