Forty-Third Legislative District

Project ID
Project Title
Estimate Total Prior Expenditures Reapprop. 2023-25 New Approp. 2023-25 Estimated New Approp. 2025-27 Estimated New Approp. 2027-29 Estimated New Approp. 2029-31 Estimated New Approp. 2031-33

360 University of Washington

20091002
Anderson Hall Renovation
28,850,000 200,000 28,650,000
20091002
Anderson Hall Renovation
11,950,000 11,950,000
30000492
College of Engineering Interdisciplinary/Education Research Ctr
46,000,000 6,534,000 39,466,000
30000492
College of Engineering Interdisciplinary/Education Research Ctr
37,200,000 37,200,000
30000808
UW Major Infrastructure
2,000,000 2,000,000
30000808
UW Major Infrastructure
72,800,000 37,500,000 3,000,000 14,300,000 18,000,000
40000049
Magnuson Health Sciences Phase II- Renovation/Replacement
64,000,000 4,500,000 1,500,000 58,000,000
40000098
UW Clean Energy Testbeds
7,500,000 7,500,000
40000099
Chemical Sciences Modernization
200,000,000 5,000,000 100,000,000 95,000,000
40000099
Chemical Sciences Modernization
40,000,000 20,000,000 20,000,000
40000100
Intellectual House - Phase 2
9,000,000 9,000,000
40000100
Intellectual House - Phase 2
3,000,000 3,000,000
40000103
UW Seattle - Asset Preservation (Minor Works) 23-25
178,450,000 33,691,000 31,543,000 36,122,000 37,729,000 39,365,000
40000132
Infrastructure Renewal
190,000,000 35,000,000 35,000,000 35,000,000 35,000,000 50,000,000
91000016
Ctr for Advanced Materials and Clean Energy Research Test Beds
29,000,000 17,000,000 12,000,000
91000016
Ctr for Advanced Materials and Clean Energy Research Test Beds
263,100,000 263,100,000
Total for University of Washington 1,182,850,000 65,734,000 57,966,000 506,391,000 204,543,000 186,122,000 72,729,000 89,365,000

461 Department of Ecology

92000193
Pier 63 Creosote Removal
1,500,000 1,500,000
Total for Forty-Third Legislative District 1,184,350,000 65,734,000 59,466,000 506,391,000 204,543,000 186,122,000 72,729,000 89,365,000