Washington State Patrol

Major Function, Agency, Project Estimate Total Prior Expenditures Reapprop. 2025-27 New Approp. 2025-27 Estimated New Approp. 2027-29 Estimated New Approp. 2029-31 Estimated New Approp. 2031-33 Estimated New Approp. 2033-35
30000290

Crime Laboratory I-5 North Corridor Consolidated Facility

State Building Construction Account - State
7,533,000 332,000 7,201,000
40000095

Crime Laboratory South Consolidated Facility

State Building Construction Account - State
113,526,000 13,526,000 100,000,000
40000072

Crime Laboratory South I-5 Corridor Consolidated Facility

State Building Construction Account - State
8,600,000 193,000 8,407,000
30000171

FTA Emergency Power Generator Replacement

State Building Construction Account - State
875,000 767,000 108,000
40000092

Fire Training Academy (FTA) Fuel Farm Refurbishment

State Building Construction Account - State
1,000,000 1,000,000
40000091

Fire Training Academy (FTA) Maintenance Building Roof Replacement

State Building Construction Account - State
300,000 300,000
40000077

Fire Training Academy Roof Replacement

State Building Construction Account - State
572,000 290,000 282,000
40000081

Seattle Crime Laboratory Generator Replacement

State Building Construction Account - State
450,000 450,000
30000240

Vancouver Crime Lab - New Roof

State Building Construction Account - State
1,594,000 112,000 1,482,000
40000097

Vancouver Crime Lab Chiller Replacement

State Building Construction Account - State
988,000 988,000

Washington State Patrol Fund Summary

State Building Construction Account - State 135,438,000 1,694,000 18,918,000 14,826,000 100,000,000
Total for Washington State Patrol 135,438,000 1,694,000 18,918,000 14,826,000 100,000,000