Eastern Washington University

Major Function, Agency, Project Estimate Total Prior Expenditures Reapprop. 2025-27 New Approp. 2025-27 Estimated New Approp. 2027-29 Estimated New Approp. 2029-31 Estimated New Approp. 2031-33 Estimated New Approp. 2033-35
40000223

Building Decarbonization Efforts

State Building Construction Account - State
25,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000
40000156

Civil Engineering Building - Applied Engineering

State Building Construction Account - State
127,500,000 7,500,000 120,000,000
40000158

Geothermal Plant - Node 1

State Building Construction Account - State
10,437,000 10,437,000
40000158

Geothermal Plant - Node 1

Climate Commitment Account - State
153,513,000 53,513,000 50,000,000 50,000,000
Total for Geothermal Plant - Node 1 163,950,000 10,437,000 53,513,000 50,000,000 50,000,000
91000027

HB 1390 – District Energy Systems

Climate Commitment Account - State
200,000 54,000 146,000
40000070

Infrastructure Renewal III

State Building Construction Account - State
10,000,000 7,853,000 2,147,000
40000114

Infrastructure Renewal IV

State Building Construction Account - State
12,000,000 2,651,000 9,349,000
40000123

Kingston Hall Renovation

State Building Construction Account - State
80,400,000 400,000 5,000,000 75,000,000
40000071

Lucy Covington Center

State Building Construction Account - State
20,280,000 2,400,000 17,880,000
40000071

Lucy Covington Center

Eastern Washington University Capital Projects Account - State
300,000 281,000 19,000
Total for Lucy Covington Center 20,580,000 281,000 19,000 2,400,000 17,880,000
40000113

Martin - Williamson Hall

State Building Construction Account - State
153,323,000 287,000 63,000 12,415,000 80,555,000 60,003,000
40000116

Minor Works: Preservation 2023-25

State Building Construction Account - State
5,375,000 1,692,000 3,683,000
40000171

Minor Works: Preservation 2025-27

State Building Construction Account - State
15,250,000 15,250,000
40000120

Minor Works: Program 2023-25

Eastern Washington University Capital Projects Account - State
6,000,000 2,205,000 3,795,000
40000119

Minor Works: Program 2025-27

State Building Construction Account - State
2,000,000 2,000,000
40000119

Minor Works: Program 2025-27

Eastern Washington University Capital Projects Account - State
3,800,000 3,800,000
Total for Minor Works: Program 2025-27 5,800,000 5,800,000
40000134

Preventative Maintenance/Backlog Reduction

Eastern Washington University Capital Projects Account - State
2,217,000 1,386,000 831,000
40000134

Preventative Maintenance/Backlog Reduction

Eastern Washington University Capital Projects Account - State
11,085,000 2,217,000 2,217,000 2,217,000 2,217,000 2,217,000
Total for Preventative Maintenance/Backlog Reduction 13,302,000 1,386,000 831,000 2,217,000 2,217,000 2,217,000 2,217,000 2,217,000
30000507

Science Renovation

State Building Construction Account - State
111,287,000 52,943,000 58,344,000
40000124

Showalter Hall Renovation

State Building Construction Account - State
86,400,000 400,000 6,000,000 80,000,000
40000112

Sports and Recreation Center Energy Improvements

Climate Commitment Account - State
9,998,000 9,998,000

Eastern Washington University Fund Summary

State Building Construction Account - State 659,252,000 65,426,000 73,586,000 47,502,000 111,335,000 190,403,000 86,000,000 85,000,000
Eastern Washington University Capital Projects Account - State 23,402,000 3,872,000 4,645,000 6,017,000 2,217,000 2,217,000 2,217,000 2,217,000
Climate Commitment Account - State 163,711,000 54,000 10,144,000 53,513,000 50,000,000 50,000,000
Total for Eastern Washington University 846,365,000 69,352,000 88,375,000 53,519,000 167,065,000 242,620,000 138,217,000 87,217,000