Kittitas County

Project ID
Project Title
Estimate Total Prior Expenditures Reapprop. 2025-27 New Approp. 2025-27 Estimated New Approp. 2027-29 Estimated New Approp. 2029-31 Estimated New Approp. 2031-33 Estimated New Approp. 2033-35

375 Central Washington University

30000456
Nutrition Science
59,580,000 59,363,000 217,000
30000766
Greenhouse Replacement
4,528,000 4,528,000
30000778
Lind Hall Phase 2
9,978,000 9,978,000
30000779
Bouillon Hall Phase 2
9,955,000 9,955,000
30000829
Shaw Smyser Upgrade
5,597,000 5,597,000
30000831
Academic Storage Facility
7,220,000 7,220,000
30000832
Aquatics Building Renovation
9,990,000 9,990,000
30000836
Arts Education
300,000 259,000 41,000
40000009
Health Education
62,205,000 62,060,000 145,000
40000081
Humanities & Social Science Complex
101,963,000 31,049,000 59,756,000 11,158,000
40000081
Humanities & Social Science Complex
7,000,000 7,000,000
40000085
Public Safety Building
34,905,000 300,000 3,371,000 31,234,000
40000087
McConnell Auditiorium Renovation
9,843,000 9,843,000
40000121
Electrical Grid Security
754,000 694,000 60,000
40000121
Electrical Grid Security
754,000 694,000 60,000
40000123
Multicultural Center
6,000,000 774,000 5,226,000
40000124
Behavioral & Mental Health Building
108,585,000 9,704,000 98,881,000
40000125
Aviation Degree Expansion
9,968,000 9,968,000
40000126
Brooks Library Renovation
86,116,000 300,000 7,412,000 78,404,000
40000161
Secondary Geothermal Module
12,464,000 12,464,000
40000162
Science Building Carbon Reduction
4,509,000 4,509,000
40000163
Emergency Backup Power System
11,773,000 11,773,000
40000165
2025-27 Decarbonization Package
12,467,000 12,467,000
40000166
Institutional Equipment Upgrades
1,000,000 1,000,000
40000166
Institutional Equipment Upgrades
1,000,000 1,000,000
40000167
Wildcat Farm Composter
1,713,000 1,713,000
40000170
Minor Works Preservation 2025-27
7,000,000 7,000,000
40000189
2027-2029 Decarbonization Package
94,263,000 94,263,000
40000190
2029-2031 Decarbonization Package
65,000,000 65,000,000
40000191
2031-2033 Decarbonization Package
82,980,000 82,980,000
40000192
2033-2035 Decarbonization Package
14,500,000 14,500,000
40000193
Minor Works Program 2025-27
1,000,000 1,000,000
91000023
Preventive Facility Maintenance and Building System Repairs
4,844,000 1,537,000 885,000 2,422,000
91000024
HB 1390 – District Energy Systems
800,000 537,000 263,000
Total for Central Washington University 850,554,000 156,967,000 90,626,000 59,501,000 124,100,000 171,593,000 190,285,000 57,482,000

465 State Parks and Recreation Commission

30000177
Lake Easton - Infrastructure Improvements
4,702,000 780,000 3,922,000
40000135
Palouse to Cascades Trail – Repair Trestles and Trail Access
2,192,000 2,192,000
40000161
Ginkgo - Interpretive Center Access Rehabilitation
1,760,000 1,760,000
40000192
Lake Easton Cabins
1,611,000 1,611,000
40000352
Wanapum Day Use Restroom Replacement
750,000 750,000
40000353
Wanapum Replace Restroom Drainfields
250,000 250,000
Total for State Parks and Recreation Commission 11,265,000 780,000 6,114,000 1,861,000 2,510,000

477 Department of Fish and Wildlife

40000162
Taneum Creek Property Acquisition Post Closing Activities
200,000 64,000 136,000

490 Department of Natural Resources

40000038
Teanaway
1,856,000 1,656,000 200,000
Kittitas County Total 863,875,000 158,687,000 90,962,000 130,214,000 173,454,000 190,285,000 59,992,000