Walla Walla County

Project ID
Project Title
Estimate Total Prior Expenditures Reapprop. 2025-27 New Approp. 2025-27 Estimated New Approp. 2027-29 Estimated New Approp. 2029-31 Estimated New Approp. 2031-33 Estimated New Approp. 2033-35

305 Department of Veterans Affairs

40000147
WWVH - Building 1 Renovation
5,000,000 5,000,000

310 Department of Corrections

30000084
WSP: HVAC & Replace Roof & Hatch Unit 7
3,484,000 3,484,000
30000107
WSP: HVAC Replacement for the East Complex Industries Bldg
4,000,000 4,000,000
30000143
Washington Corrections Center: Transformers and Switches
20,585,000 18,906,000 1,679,000
30000184
WSP: Unit Ten Roof & HVAC Replacement
4,600,000 4,600,000
30000254
WSP: Unit Eight Roof and HVAC
14,725,000 2,663,000 12,062,000
30000272
WSP: Tuck Pointing Masonry Walls and Buildings
4,000,000 2,000,000 2,000,000
30000279
WSP: Insulate Steam Stations and Lines
3,348,000 1,674,000 1,674,000
30000673
WSP: Waterline Utilities Replacement
2,426,000 1,213,000 1,213,000
30000676
WSP: HVAC Replacement - WC Industries
3,388,000 1,694,000 1,694,000
30000682
WSP: Roof Replacement - WC Old Warehouse
3,581,000 3,581,000
30000761
WSP: IMU North Roof
2,892,000 2,892,000
30000878
WSP: EC Admin Repair
15,200,000 15,200,000
30000969
WSP: Replace HVAC Bldg C (IMU South)
6,431,000 1,286,000 5,145,000
30000970
WSP: Replace HVAC Bldg A (N Admin)
1,400,000 1,400,000
30001025
WSP: IMU North Boilers
12,256,000 12,256,000
40000080
WSP: Storm Drain System Issue
1,500,000 750,000 750,000
40000273
WSP: SC Sustainable Practice Lab HVAC
2,882,000 1,441,000 1,441,000
40000279
WSP: EC Admin HVAC and Roof Replacement
6,000,000 1,200,000 2,400,000 2,400,000
40000282
WSP: Unit Four Roof
3,790,000 1,895,000 1,895,000
40000413
Inpatient Psychiatric Unit
350,000 326,000 24,000
40000463
WSP: Replace Smoke Control Dampers
5,000,000 5,000,000
40000526
WSP: IMU South Fire Protection & Smoke Dampers
4,622,000 4,622,000
40000542
WSP: Add Two Towers in the West Complex
10,742,000 2,260,000 8,482,000
40000606
WSP: C-40 East Complex IAC Replace Roof
1,500,000 1,500,000
40000743
WSP: D50 and D51-EC Unit 1 Roof Replacement
1,423,000 1,423,000
40000746
WSP: New Power House Boilers
15,000,000 15,000,000
40000747
WSP: Water Tower Removal
2,553,000 2,553,000
40000748
WSP: Model Toxics Control Act Cleanup Implementation
8,000,000 8,000,000
40000771
WSP: Replace Roofs on Bldgs K10-K80
8,000,000 4,000,000 4,000,000
40000779
WSP: District Energy Decarbonization
62,035,000 300,000 15,520,000 46,215,000
92000037
WSP: Unit Six Roof Replacement
13,994,000 1,377,000 12,617,000
Total for Department of Corrections 249,707,000 20,609,000 18,942,000 2,560,000 57,094,000 64,677,000 20,376,000 65,449,000

699 Community and Technical College System

30001452
Walla Walla Science and Technology Building Replacement
10,639,000 10,603,000 36,000
Walla Walla County Total 265,346,000 31,212,000 18,978,000 62,094,000 64,677,000 20,376,000 65,449,000