Twenty-Fifth Legislative District

Project ID
Project Title
Estimate Total Prior Expenditures Reapprop. 2025-27 New Approp. 2025-27 Estimated New Approp. 2027-29 Estimated New Approp. 2029-31 Estimated New Approp. 2031-33 Estimated New Approp. 2033-35

365 Washington State University

40000372
Puyallup Washington Animal Disease Diagnostic Lab Facility
23,000,000 3,000,000 20,000,000

465 State Parks and Recreation Commission

30000521
Millersylvania Replace Original 1940's Water System
3,299,000 3,299,000

477 Department of Fish and Wildlife

40000246
SRKW Puyallup Hatchery Expansion
5,985,000 959,000 5,026,000

699 Community and Technical College System

40000293
Pierce Puyallup: STEM building
41,969,000 39,304,000 2,665,000
Total for Twenty-Fifth Legislative District 74,253,000 39,304,000 2,665,000 3,000,000 23,299,000 959,000 5,026,000