The Evergreen State College
Minor Works Preservation 2025-27
40000103
Projects include work to extend the useful life of college facilities, such as roof renovations, energy efficiency upgrades, infrastructure upgrades, steam and condensate system renovations, and upgrades to the campus telephone system and underground storage tanks. These projects are required to protect state assets, reduce the deferred maintenance backlog and prevent further damage to property and extend the life of facilities.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 18,500,000 | 102,046,000 | 120,546,000 |
Funds: State Building Construction Account - State | 85,007,000 |
Funds: The Evergreen State College Capital Projects Account - State | 35,539,000 |
Preventive Facility Maintenance and Building System Repairs
40000140
This project will support the college’s preventive maintenance efforts to ensure the longevity of existing facilities and building systems in newly renovated and constructed spaces.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 880,000 | 6,100,000 | 6,980,000 |
Funds: The Evergreen State College Capital Projects Account - State | 6,980,000 |
Evans Hall Decarbonization
40000142
The Evans Hall decarbonization predesign and design will investigate severing it from the central utility steam plant. In its place, heat pumps and electric boilers with sufficient capacity to meet the heating, cooling, and domestic hot water needs will be evaluated.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 4,659,000 | 43,802,000 | 48,461,000 |
Funds: State Building Construction Account - State | 48,461,000 |
Dormitories Decarbonization
40000143
This project will address inefficient and failing HVAC systems by disconnecting dormitories from the central steam distribution system and provide locally generated domestic hot water and HVAC heating. This project will be phased over multiple biennia.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 7,000,000 | 13,287,000 | 20,287,000 |
Funds: State Building Construction Account - State | 20,287,000 |
Labs 1 & 2 Third Floor Renovation
40000145
Funding is provided to conduct a predesign study for Labs 1 and 2. Once completed, this project will conclude the phased lab renovations. The third-floor office area is last to receive an improvement from the original construction in 1976. The Laboratory Wing renovation will provide modular class and research facilities that meet the college’s academic needs.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 298,000 | 18,881,000 | 19,179,000 |
Funds: State Building Construction Account - State | 19,179,000 |
Minor Works Program 2025-27
40000146
Funds updates to existing faculty and LAB staff assigned spaces in LAB I/II and relocates the college library archives.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 3,836,000 | 7,000,000 | 10,836,000 |
Funds: State Building Construction Account - State | 2,336,000 |
Funds: The Evergreen State College Capital Projects Account - State | 8,500,000 |