Military Department
Moses Lake Readiness Center Renovation
40000194
State funding and federal authority is provided for the construction phase of the renovation project.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 391,000 | 5,151,000 | 925,000 | 0 | 6,467,000 |
Funds: General Fund - Federal | 3,656,000 |
Funds: State Building Construction Account - State | 2,811,000 |
Wenatchee Army National Guard Aviation Support Facility
40000305
Funding is provided for predesign of a future Army Aviation Support Facility at Wenatchee.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 450,000 | 8,217,000 | 8,667,000 |
Funds: State Building Construction Account - State | 8,667,000 |
Yakima Training Center Army NG Combat Fitness Training Facility
40000314
Federal expenditure authority is provided to design an Army Combat Fitness Training Facility at the Yakima Training Center.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 600,000 | 6,000,000 | 0 | 6,600,000 |
Funds: General Fund - Federal | 6,600,000 |
Minor Works Program 2025-27 Biennium
40000345
State funding and federal spending authority is provided to upgrade and renovate multiple facilities across the state to improve working conditions, provide energy efficiencies, and extend the life of facilities.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 9,885,000 | 0 | 9,885,000 |
Funds: General Fund - Federal | 8,444,000 |
Funds: State Building Construction Account - State | 1,441,000 |
Minor Works Preservation 2025-27 Biennium
40000346
State funding and federal spending authority is provided to repair and restore multiple state and federally supported facilities across the state.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 17,792,000 | 0 | 17,792,000 |
Funds: General Fund - Federal | 10,290,000 |
Funds: State Building Construction Account - State | 7,502,000 |
Camp Murray Mechanical Security Barricade Repair
40000347
Federal spending authority is provided for the repair of mechanical barricades and traffic spike system at Camp Murray.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 2,660,000 | 0 | 2,660,000 |
Funds: General Fund - Federal | 2,660,000 |
Joint Base Lewis-McChord Army Aviation Support Facility 1 HVAC
40000348
Federal expenditure authority is provided for replacement of the HVAC system at the Army Aviation Support Facility at Joint Base Lewis McChord.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 4,462,000 | 0 | 4,462,000 |
Funds: General Fund - Federal | 4,462,000 |
Yakima Training Center 960 (MATES) HVAC System Replacement
40000351
Federal expenditure authority is provided for replacing the HVAC at Building 960 at the Yakima Training Center.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 5,741,000 | 0 | 5,741,000 |
Funds: General Fund - Federal | 5,741,000 |
Yakima Training Center Military Vehicle Parking Repair
40000352
Federal expenditure authority is provided for repair of damaged areas of the military organizational vehicle lot at the Yakima Training Center.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 3,623,000 | 0 | 3,623,000 |
Funds: General Fund - Federal | 3,623,000 |
Geiger Field 200 Restoration
40000354
State funding and federal expenditure authority is provided for the renovation of Building 200 at Geiger Field.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 1,002,000 | 8,702,000 | 9,704,000 |
Funds: General Fund - Federal | 5,482,000 |
Funds: State Building Construction Account - State | 4,222,000 |
Geiger Field 300 Homeland Response Force (HRF) Alteration
40000355
Funding is provided to renovate Building 300 at Geiger Field from a field maintenance shop to a readiness center.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 300,000 | 7,337,000 | 7,637,000 |
Funds: State Building Construction Account - State | 7,637,000 |
Geiger Field 402 Renovation
40000356
State funding and federal expenditure authority is provided to renovate the infrastructure at Building 402 at Geiger Field.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 1,002,000 | 8,681,000 | 9,683,000 |
Funds: General Fund - Federal | 5,183,000 |
Funds: State Building Construction Account - State | 4,500,000 |
Joint Base Lewis-McChord 9608 (UTES) Interior Modification
40000357
Federal expenditure authority is provided to renovate Building 9608 infrastructure at Joint Base Lewis-McChord.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 782,000 | 6,791,000 | 7,573,000 |
Funds: General Fund - Federal | 7,573,000 |
Sedro Woolley Field Maintenance Shop Renovation
40000366
Federal expenditure authority is provided for a remodel and renovation of the Sedro Woolley Field Maintenance Shop.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 5,520,000 | 0 | 5,520,000 |
Funds: General Fund - Federal | 5,520,000 |
Tumwater Field Maintenance Shop
40000367
Funding is provided to design and construct a new Field Maintenance Shop in Tumwater.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 480,000 | 3,700,000 | 247,000 | 4,427,000 |
Funds: State Building Construction Account - State | 4,427,000 |
Yakima Training Center (MATES) Renovation
40000369
Federal expenditure authority is provided for renovation work at the Yakima Training Center.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 7,950,000 | 0 | 7,950,000 |
Funds: General Fund - Federal | 7,950,000 |